Planning Report - 13 Eumundi-Noosa Road, Noosaville QLD 4566 - Dual Occupany
Performance outcomes Acceptable outcomes Response
1. minimal disturbance to neighbouring
properties and properties along the
haulage route; and
2. Council’s road infrastructure
including pavements is not adversely
affected.
Extent of earthworks AO8 Complies with AO8
PO8 All earthworks, including cut and fill batters,
Any earthworks undertaken will be contained
The layout of the development provides adequate, retaining walls and the like are contained within
within the subject site.
clearly defined and easily accessible— the subject site.
1. on-site vehicle parking and
manoeuvring areas; and
2. loading and manoeuvring areas for
delivery and service vehicles.
Sloping sites AO9 Complies with AO9
PO9 Cut or fill is less than 1.5 metres in depth relative
Any cut or fill will be less than 2m in depth relative
On sloping sites development follows the natural to the natural ground level.
to the natural ground level.
landform wherever practical and excavation or
filling is minimal.
Infrastructure protection No acceptable outcome provided Complies with PO10
PO10
The proposed development will ensure that
Earthworks and vehicular access do not adversely
earthworks and vehicular access will minimise any
impact on the capacity, operations and
adverse impact to the capacity, operations and
maintenance of existing infrastructure.
maintenance of existing infrastructure.
Development Application: 13 Eumundi Noosa Road, Noosaville Noosa Plan 2020: Amendment 1 Effective date: 25/09/2020
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewSearchable page text hides email addresses. Original files are unchanged and may show email addresses.