Part B - Attachments A to D
Attached to the e-mail Other Change Application – 132002.220285.5.
Specific Outcome Probable Solution Response
O10 Roads and stormwater drainage S10.1 Roads and stormwater drainage follow the edge of existing R10 Complies
infrastructure are located and aligned so as disturbed areas, or alternatively, these works are co-located
to— within a combined utility corridor; The proposed drainage works will comply. See Attachment G –
Hydraulic Services Plan. The site is not identified as having
a. minimise disturbance to native AND significant biodiversity values.
vegetation and/or other habitat areas; Roads avoid native vegetation and provide for fauna
S10.2
b. protect and maintain wildlife corridor underpasses and associated fencing where appropriate;
movements and the safety of native AND
fauna;
S10.3 Road infrastructure within or adjacent to native habitat
c. minimise changes to the hydrological
incorporates fences which allow for protected wildlife
regime, including drainage patterns, movement and controls unrestricted access of domestic cats
run-off and water quality; and dogs; AND
d. avoid crossing watercourses,
S10.4 Native vegetation is protected from clearing or construction
drainage lines and wetlands, but
activities by—
where such crossings are
unavoidable, disturbed areas are a. clearly marking vegetation to be retained with flagging
reinstated and revegetated on tap;
completion of works; and b. installing protective fencing around the dripline of
e. minimise bulk earthworks.. vegetation; and
c. ensuring stock piling, storage and vehicle parking occur
outside the areas of vegetation to be retained;
AND
S10.5 Low impact construction techniques are used around areas
of vegetation to be retained to minimise interference with the
vegetation.
O11 Roads and stormwater drainage No solution provided R11 Will Comply
infrastructure is proven to be suitable for its
use prior to Council accepting the The proposed drainage works will comply. See Attachment G –
dedicated asset. Hydraulic Services Plan.
O12 Alignment of stormwater drainage S12.1 The location, design and construction of stormwater R12 Complies
infrastructure is to allow for easy access for drainage structures is in accordance with Sections 4 and 5
the ongoing maintenance by Council. of PSP5, Engineering Design Standards - Roads, Drainage The proposed drainage works will comply. See Attachment G –
and Earthworks; Hydraulic Services Plan.
AND
S12.2 Where infrastructure is located on private land an easement
is dedicated over the infrastructure in accordance with
Section 4 of PSP 5, Engineering Design Standards – Roads,
Drainage and Earthworks.
14.147 Frontage works
O13 Development is provided with external S13.1 The following infrastructure components already exist at the R13 Complies
roadworks along the full extent of the frontage of the site or are provided at the developer’s
frontage of the site to an appropriate expense— Driveways and access are already in place and not proposed to be
standard having regard to the specified changed.
a. full width sealed road;
function of the road.
b. concrete kerb and channel where appropriate;
c. forming and grading to footpaths;
December 2017 Cardno 7
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.