23688 DA - COMPILED Decision Notice [As Published] · 132004.240015.4

of 10

Text shows just the words. Original shows the document exactly as it was published.

NOOSA COUNCIL IDAS Development Application Decision Notice                                                            6


                  All earthworks must incorporate shallow surface spoon drains at the base and along the high side
                    of the cut. Drains must have an efficient outflow down -slope and clear of the construction area
                    and should utilise absorption and a means of disposal to minimise the stormwater erosion.
                  All liquid waste or stormwater runoff should be disposed of in a manner that does not compromise
                    the stability of the site, existing and proposed structures.
                  All earthworks must ensure the stability of neighbouring structures is maintained through not
                    undermining their foundations.
                  Any filling within the allotment shall be placed and compacted in accordance with AS3798-1996 to
                    a level sufficient to achieve a Level 1 certification with a minimum relative field density of 95%.
                  Vegetation cover within the allotment is to be preserved or replaced where removed for
                    construction.
Erosion and Sediment Control

21.       To protect the environment against siltation/sediment export or soil erosion as a result of this
          development, an erosion and sediment control plan shall be submitted in conjunction with any
          Development Permit for Building Works. Site control measures such as silt fencing, controlled gravel
          access to the site and controlled disposal of waste, may be necessary. Prior to commencement of
          building works, all physical site control measures shall be installed, and the plan adhered to.
Building Services

22.       A contour survey of the subject site is to be carried out by a Licensed Surveyor and is to be submitted to
          Council at the time of application for building approval. Such survey shall set out the natural surface
          levels of the site and the position of buildings on the site.

23.       A verification survey of the building is to be carried out by a Licensed Surveyor and a certificate lodged
          with Council at completion of the work confirming compliance with the minimum required floor level and
          the maximum building height above natural surface, required by the provisions of the Planning Scheme.

24.       The Geotechnical report submitted as part of your application has been appraised and approved subject
          to the following conditions: -

          24.1. There is to be no uncontrolled discharge of water onto the slope;

          24.2. Stripping of vegetation for construction purposes should be minimised. If vegetation is destroyed it
                should be reinstated immediately after construction is completed;

          24.3. Additional load due to fill, construction equipment or stockpiled materials should not be located on
                the dune slope;

          24.4. The use of vibratory equipment of any kind is not permitted to be used, including vibrating rollers,
                the use of vibrating installation techniques for sheet piling and other construction vibrations caused
                by excavating, earthmoving or demolition machinery or other similar construction techniques;

          24.5. The construction management plan as defined by Recommendations 4.3 Construction and 4.4
                Stormwater in the geotechnical report prepared by Sunshine Coast Geotechnical Pty Ltd dated 2
                February 2004 is to be adhered to;

          24.6. A condition survey is to be carried out of adjoining buildings, structures and services prior to any
                demolition works or construction works taking place on site. If distress already exists, a
                photographic survey shall be undertaken, the distress measured and a plan to monitor changes to
                distress shall be implemented. A copy of this report is to be submitted to Council within 5 business
                days of survey and prior to construction work proceeding;

          24.7. Copies of all inspection reports by engineers are to be submitted to Council within 5 business days
                of the inspection taking place;

          24.8. Boundary wall movement shall be monitored throughout construction by a RPEQ and if movement
                occurs construction is to be stopped immediately and appropriate action is to be taken to arrest the
                movement. Further work shall only take place after a re-assessment of the conditions on site;




KP o:\database\onestop\decision.doc

Used in these records

About this file

File size
45 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

23688 DA - COMPILED Decision Notice [As Published].pdf · 45 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.