rehabilitated as required. Therefore the overall stormwater quality being discharged from the site
will likely be improved, and there will not be an impact on the water quality of Lake Weyba.



Regular water quality monitoring will be used to ensure that stormwater being discharged from site
is of suitable quality.


Based upon the above assessment and recommendation it is considered the                      proposal can be
conditioned to comply with the requirements of the Transport Roads and Drainage Code.




Water Sensitive Design Code



Included within Appendix 18 Gilbert & Sutherland Pty Ltd have established a proposed Integrated
Water Cycle    Management Plan. The plan concludes the following to ensure compliance with the
Water Sensitive Design Code.
            .    Three main factors taken into consideration: The high rainfall; Limited opportunities

                 for open space irrigation due to soil, groundwater and space limitations; and Access
                 to both the potable water supply network and the Noosaville STP.

            .    Sustainable   supply through rainfall harvesting, (but being problematic for the
                 sustained irrigation or domestic re-use from the effluent streams)
            .    Comprising rainwater harvesting, both to maximize the off-set of potable demands
                 from the municipal supply network and to improve the quality ofstormwater runoff.
            .     The provisional clarification that the augmentation to the Noosaville STP might

                 proceed on a schedule allowing for receipt of sewage from Noosa on Weyba, and the
                 results of the soil and groundwater investigations all-but precluding sustained open

                 space irrigation, meant the focus of the IWCM investigations was primarily on the
                 IWCM Option 4, comprising rainwater harvesting, both to maximize the off-set of

                 potable demands from the municipal supply network and to improve the quality of
                 stormwater runoff.

            .    The   analysis of the rainfall data available for the Tewantin RSL Park, Eumundi-
                 Crescent Road and Noosaville sites indicated mean annual rainfall in the range from

                 1500mmja to 1700mmja. A rainwater balance for a typically sized residence with a
                 net contributing roof area of 100m2, indicated substantial demand off-set potential

                 for rain tanks of 10kL capacity, and this tank size was then selected for the
                 assessment of the overall precinct scale demand off-set.

            .    It was determined from the precinct analyses that a 10kL rain tank configuration
                 could supply approximately 96% of the standard residential household demands for
                 toilet   cisterns, garden   irrigation   and   laundry   use.   This   in   turn   represents
                 approximately 25-30% of the total household demand, representing a significant,
                 sustained offsetfrom the bulk water supply system serving the Noosa area.
            .    The apartment blocks and townhouse complexes were modelled with communal tank

                 systems and the performance of these could be improved once the space constraints
                 for tanks is known. The reticulation would however serve each residence equally. A
                 provisional residential tank configuration is presented in Figure C2 in Appendix 1 of
                 the Integrated Water Cycle Management Plan, designed to combine two 5kL tanks
                 into a functional 10kL unit, also providing an important retention and throughflow
                 barrier for improving the quality of storm water runoff.
            .    The rainwater harvesting strategy lends itself to cost-effective, staged development
                 across   the estate and minimizes the need for dual-pipe reticulation and control

                 systems. It should be developed in conjunction with bio-retention swales and basins,
                 treating storm water runoff prior to discharge to the creeks.

                                                                                                           56

Used in these records

About this file

File size
35.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Part 2 of 37 Noosa on Weyba Town Planning Assessment Report MCU12_0208.pdf · 35.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.