Council archive · source document
Decision Notice - Change to an Existing Approval [As Published] · 132003.220735.7
2003/220735
106.2 During the construction stage, weekly inspections, monthly water quality monitoring and
monitoring after significant rainfall events (at least two per year) shall be undertaken for:
106.2.1 suspended solids and turbidity,
106.2.2 temperature,
106.2.3 salinity,
106.2.4 total nitrogen,
106.2.5 total phosphorous,
106.2.6 pH,
106.2.7 trash and gross pollutants, and
106.2.8 dissolved oxygen.
106.3 During the establishment and operational stages, water quality monitoring shall be
undertaken every third month and monitoring after significant rainfall events (at least two
per year) shall be undertaken for:
106.3.1 total nitrogen,
106.3.2 total phosphorous,
106.3.3 suspended solids and turbidity,
106.3.4 pH,
106.3.5 salinity,
106.3.6 temperature,
106.3.7 dissolved oxygen,
106.3.8 trash and gross pollutants,
106.3.9 algal count and identification, and
106.3.10 faecal coliforms.
106.4 The Developer shall continue this water quality monitoring for a period of 3 years from
completion of the final stage of construction. In addition, the Developer shall undertake
inspections for erosion and deposition, the build-up of trash and gross pollutants, and
other water pollution. These inspections will be carried out every third month as well as
after significant rainfall events, for a period of 3 years from completion of the final stage of
construction.
106.5 An operational stage Water Quality Management Plan shall be prepared to address water
quality performance targets, water treatment devices, water quality maintenance,
requirements for stormwater management measures and devices, contingency measures
for aquatic plant growth, loss of vegetation in swales and filter strips, pollution response
and algal blooms. It shall also include a mosquito management strategy and a cane toad
management strategy. The plan shall demonstrate compliance with the prescribed water
quality objectives. This Water Quality Management Plan shall be incorporated into the
Operational Stage EMP.
106.6 Responsibilities shall be clearly delineated.
106.7 Non-compliance with prescribed water quality standards will trigger the implementation of
measures to rectify the problem(s).
Page 16 of 32
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Change to an Existing Approval [As Published]Related documentApplication case desk ↗
About this file
- File size
- 130 KB (small file)
- File type
No other editions are linked here.