106.8 During construction and establishment stages, monthly reports on monitoring, incidents,
corrective action and plan updates shall be submitted to Council. These reports shall be
submitted in a form acceptable to Council and shall highlight any non-standard results.
The format and content of these reports shall be in hard copy and digital form, generally in
accordance with the following:
106.8.1 including tables of the monitoring results (digital form should be in Excel);
106.8.2 include individual charts plotting the results for all parameters required in the
monitoring (digital form should be in Excel);
106.8.3 include a brief written discussion of the results and recommend any necessary
actions.
Water Quality Devices
107 The Developer shall install water quality control devices generally in accordance with the
Stormwater and Water Quality Management Plan. Detailed staging plans and specifications,
based on and generally in accordance with the Plan shall be prepared and submitted (after
consultation with officers of the Council) with the relevant applications for operational works.
108 Detention Basins D & E shall be constructed and operated in a manner that does not adversely
affect flood levels elsewhere on the floodplain, cause environmental harm or impact upon the
adjacent wetland, tidal or intertidal areas.
Drainage Works
109 The Developer shall complete the drainage works progressively in conjunction with development
of the site and generally in accordance with the approved Stormwater and Water Quality
Management Plan. Detailed drainage plans and specifications, based on and generally in
accordance with the approved Drainage Plan, the Construction EMP and these Conditions, shall
be prepared and submitted (after consultation with officers of the Council) with the relevant
applications for operational works.
110 All drainage works as required by the Drainage Plan shall be provided by the Developer at its
own cost.
Acid Sulfate Soils Management Plan
111 Prior to approval for a Development Permit for Operational Work for any component or stage of
the development, an Acid Sulfate Soils (ASS) Management Plan shall be provided for any
excavation works undertaken in areas below 5m AHD. The Management Plan shall outline the
ASS investigations undertaken and the management procedures to be undertaken in that part of
the site in accordance with State Planning Policy 2/02 ‘Planning and Managing Development
Involving Acid Sulfate Soils’.
112 The Acid Sulphate Soils Management Plans for each component or stage of the development
shall generally be in accordance with the Acid Sulphate Soil Investigation Report for the whole
site, prepared by Soil Surveys (dated July 2003).
113 At the group title components of the site the developer shall provide for refuse collection
arrangements that are in accordance with an approved Refuse Management Plan. Where there
are any communal refuse collection points a suitably screened wash down area is required with
a cold-water tap, hose and drain outlet connected to sewer. The drain outlet is to be designed to
prevent stormwater entry to the sewerage system.
114 Street litter bins to a design approved by Council, shall be supplied and installed at the
developers expense at agreed locations.
115 An approved waste management plan must be approved by Council’s Manager of
Environmental Health prior to the commencement of operational works.
The existing plan dated 29 August 2003 is deficient in adequate details of:
Page 17 of 32
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Change to an Existing Approval [As Published]Related documentApplication case desk ↗
About this file
- File size
- 130 KB (small file)
- File type
No other editions are linked here.