Skip to the record
Mmm.. taste the original NoosaWatch™

Original source · versioned page text

Attachment 5 - Deed of Variation to Infrastructure Agreement (22.01.20)

of 220

Page text read automatically using OCR, there may be inaccuracies

 

NOOSA COUNCIL IDAS Development Application Decision Notice 23

163.

164.

165.

166.

. 167.

168.

169,

170.

171.

172.

173.

All infrastructure shall be kept clear of the OS3 area including the service roadway (with the exception
of the 5 metre area at the western end of building D of the Showroom Component) and the garbage
collection area. Should part of the existing road reserve adjoining the subject site to the north be
included into the site following the dedication of the land for proposed Walter Hay Drive, it is accepted
that this area of land can contribute towards the OS3 buffer area to satisfy the requirement for the
provision of OS3 under this development permit.

Deleted.
External Works Other Than Roads

. Any necessary stormwater drainage systems required by the any external roadworks fronting the

Proposed development as required by these conditions of approval, will need to be constructed by the
applicant as part of those works to the reasonable satisfaction of the Manager Land Development.

Any necessary augmentation or installation of services will also need to be undertaken by the
applicant as part of this development to the reasonable requirements of the Council, The services will
need to be able to cater for the ultimate development of the SBC.

Pedestrian/Cycle Access

The applicant shail undertake ail work indicated on Pedestrian and Cycle Management Plan submitted
as Annexure 6 as part of the representations to the decision notice issued 1 May 2003. The applicant
shall construct all cycleways and pathways as shown on the Pedestrian and Cycle Management Plan.
To this end, the applicant is required to construct a shared pedestrian and cycleway pathway in lieu of
the pedestrian pathways indicated in black on the Pedestrian and Cycle Management Plan.

The applicant will design and construct all works required by the approved Pedestrian and Cycle
Management Plan for the SBC, subject to any modifications required by these conditions of approval.

The applicant will construct access from the SBC pedestrian and cycleway links to the existing
pedestrian/cycleway under Eenie Creek Road, which meets disabled access tequirements and has
good sight lines into the pedestrian/cycleway tunnel under Eenie Creek Road generally in accordance
with option 2 on plan 4024 S26B by MPN Consulting Pty Ltd.

The applicant will design and construct access from the pedestrian and cycleways shown on the
Pedestrian and Cycleway Management Plan to the proposed pedestrian/cycleway under Walter Hay
Drive, which has good sight lines into the structure. The applicant will be required to contribute 50%
towards the cost of the pedestrian/cycle underpass proposed under Walter Hay Drive.

The applicant will design and construct the external pathways for cycles and pedestrians on Eenie
Creek Road from Noosa Eumundi Road to the SBC access as part of this development.

Stormwater Drainage & Water Quality

A Stormwater Management Plan for the site including revegetation and remediation shall be prepared
and submitted prior to the issue of a development permit for operational works to the reasonable
satisfaction of the Manger Land Development. The Stormwater Management Plan shall be generally in

accordance with URS's Report of 19 June 2003” and include “and shall be implemented by the
applicant. ,

The Stormwater Management Plan will address the following:
173.1. Deleted.

173.2. Gross pollutant traps shall be installed inline on the piped systems for all paved areas that
do not fall to the proposed bio-retention devices prior to the run off entering OS7;

173.3. All primary treatment of runoff will be outside the open space area OS7 to ensure
compliance with MP2;

173.4. Deleted.

173.5. The bio-retention areas within the car parks must be large enough to allow the proposed
planting to thrive and have a viable root system;

A :\dalabase\onestop\decision.doc Page 55

Log in to download the original (Attachment 5 - Deed of Variation to Infrastructure Agreement (22.01.20).pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.