GENERAL COMMITTEE MEETING AGENDA 14 FEBRUARY 2022
Page 88 of 99
GENERAL COMMITTEE MEETING AGENDA 14 FEBRUARY 2022
Corporate Plan Key Operational Initiatives Outcomes Responsible Update Status Q1 Q2
Focus Areas Areas/Officers
4.8 Undertake long | Bridge Renewal Program Replacement and upgrading | Infrastructure | Cooran Tablelands Rd and Kin Kin Wahpunga —_| On track | On track
term financial of bridges to improve the Planning, Lane hinterland bridges construction commenced
sustainability road network and to deliver | Design & Oct21. Forecast Cooran Tablelands PC Feb22
planning economic benefits and Delivery. and Kin Kin Wahpunga forecast PC before Jun22
ee a ae ‘ INpIEV cron eet Me NaGeIne ee Cooroy Belli Creek and Lawnville Rd, hinterland
outcomes D Done bridges design is completed and tender phase
esign commences Jan22.
Delivery
Manager Tewantin Lake Doonella bridge is undergoing
options analysis for remediation and final report
due Feb22
Garth Prowd bridge undergoing options
assessment for remediation and pathway
widening.
Shire pedestrian bridges, Alec Loveday and
Cooroy Gumtree for remediation are in planning
and environmental approvals.
Asset management renewal Maintenance of assets to Asset Planning/ | Delivery of Shire Level 3 Bridge and Structure On track | On track
program required standards and Asset Planning condition assessments currently underway.
achievement of sustainable | Coordinator | shire reseal program currently over 50%
outcomes in safety, deli and invoiced
minimising lifecycle and SINETER? ANG INVOICEC.
project delivery costs Shire Stormwater CCTV Condition Assessment
program underway.
Noosa Heads Parade Corridor | Improve community Infrastructure Noosa Parade Corridor upgrade construction Ontrack | On track
storm water drainage upgrade | connectivity and create a Planning, tender has been awarded post endorsement by
collective vision. Foster Design & council in Dec 22 period. Prelims onsite expected
successful social networks | Delivery/ to mobilise Feb 22 and completion forecast 31
and benefit multiple Infrastructure | Oct 22 prior to Triathlon event.
stakeholders Planning
Design &
Delivery Mgr
Page 88 of 99See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.