Attachment 8 - Site Based Stormwater Managment Plan · MCU22/0118
Plans and drawings: the text below has words only, no drawings.
Very large file (34.8 MB): may take a few minutes to open.
RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads
22366 C R10 R003 (04.07.22)
July 2022
Refer to Appendix A for the detailed survey for further information regarding the existing stormwater
infrastructure.
Note: A diversion swale exists within existing RACV Noosa Resort along the development sites
northern boundary internal to the resort development property. ADG refer reader to previous site
reporting documents for details.
4.2 Lawful Point of Discharge (LPD)
4.2.1 Existing LPD
Based on information gathered via survey and contour data, aerial imagery and site investigation it
has been determined that the subject site discharges stormwater flows via a combination of pipework
and overland flow west towards Weyba Creek.
4.2.2 Proposed LPD
It is proposed to maintain the existing ultimate lawful point of discharge being Weyba Creek to the
west.
Refer to Appendix C for the Preliminary Layout Plans prepared by this office.
4.3 External Catchment
No significant upstream catchment directly acts on the developable site area, other than the carpark
extends beyond the boundary line. The area within Sanctuary Drive discharges to the existing council
infrastructure with the road via kerb and channel adapters, remain unchanged.
Refer to Appendix A for the detailed survey for further information regarding the existing site
features.
5 STORMWATER QUANTITY ASSESSMENT
The aim of the stormwater quantity assessment is to ensure that the development shall impose no
adverse effects on downstream properties or receiving water bodies and that the conveyance of
flows will be in a safe manner with minimal risk of human endangerment as well as the following
objectives:
Address the need for stormwater quantity control measures.
Ensure there is no actional impacts from the subject site for events up to and including the 1% AEP
event.
Ensure proposed quantity control measures detain and convey flows in accordance with QUDM
(2017) minimum freeboard recommendations.
5.1 Proposed Development and Associated Issues
In this development, the developable site area leads to negligible increase in peak flows downstream
of the subject site and immediately discharges to Weyba Creek, hence it is considered unnecessary
to include provision for stormwater quantity management. This is beneficial during any storm event,
as the short time of concentration will allow the runoff from the site to be quickly dissipated from the
area before the onset of the peak Weyba Creek flow and corresponding tidal effects.
BRISBANE / SYDNEY / MELBOURNE / GOLD COAST / SUNSHINE COAST / DARWIN / PERTH Page 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 8 - Site Based Stormwater Managment Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 34.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.