e. include details of proposed flocculants and automatic dosing systems for sediment
basins, including jar testing results. Demonstrate the suitability of the proposed
flocculant having regard to the downstream receiving environment and water quality;
and
f. include the results of all soil investigations undertaken for the site and on which the
E&SCP is based.
41. A construction hold point inspection with a Council delegate is required following the removal
of existing ground cover (i.e., grass) and prior to the commencement of the bulk earthworks.
At the time of the inspection, the erosion and sediment controls prescribed by the supervising
RPEQ or CPESC must be installed in accordance with current best practice standards.
Written certification from the supervising RPEQ or CPESC must be provided to Council
certifying that the on-site controls satisfy the conditions of this approval.
42. A logbook of all Erosion & Sediment Control (E&SC) activities must be prepared for the
development and maintained until the completion of the works. The logbook must be made
available to the Council upon request, within five (5) business days of the date of the request.
Each entry into the logbook must document the extent of works, the date the works occurred
and any observations or notes. It is expected that logbook entries may include, but are not
limited to:
a. amendments to the E&SC plan(s);
b. maintenance of any erosion and sediment controls;
c. emptying of detention basins (with Discharge Authority Certificates);
d. inspections by the supervising RPEQ or CPESC; or
e. any breaches of sediment exiting the site.
43. Prescribed Water Contaminants (as defined in the Environmental Protection Act 1994) must
not be released from the site or to waters within the site, or be likely to be released should
rainfall occur, unless all reasonable and practicable measures are taken to prevent or
minimise the release and concentration of contamination. These measures must be
designed, implemented and maintained in accordance with “Best Practice Erosion and
Sediment Control” published by the International Erosion Control Association (Australasian
Chapter) (IECA, 2008), to the extent that such measures and practices are also consistent
with the following:
a. Minimise erosion:
i. Restrict the extent of clearing to that necessary for access to and safe
construction of the approved works;
ii. Protect vegetation in all other areas of the site;
iii. Minimise the duration of soil exposure by undertaking land clearing and
stabilisation according to the rainfall erosion hazard as specified in IECA (2008)
Tables 4.4.2 and 4.4.7
iv. Prior to either the approval of the plan of survey for the development or
commencement of use, all site surfaces are to be effectively stabilised using
methods that will continue to achieve effective stabilisation in the medium to
long term. For the purpose of this condition, an effectively stabilised surface is
defined as one that does not or is not likely to result in visible evidence of soil
loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead to
water contamination.
b. Manage concentrated stormwater flows:
i. Implement drainage and erosion control measures (including contingency
measures), prior to rainfall, which prevent or minimise rill erosion and gully
erosion.
Page 31 of 39
Document Set ID: 23843933
Version: 14, Version Date: 05/09/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Negotiated Report (Representations made) MCU24 0125, OPW24 0150 & RAL24 0021 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.9 MB (small file)
- File type
No other editions are linked here.