Town Water Supply
33. The site shall be connected to Council’s existing town water supply and be constructed in
accordance with Council’s standards and requirements at no cost to Council.
34. Each water connection to the water reticulation system shall extend to the property boundary
and be metered. Where multiple units are served by a single service, multiple water meters to
each individual unit shall be installed. All fees for the supply of water meters shall be paid to
the Council.
Service Easements
35. A registered easement shall be created over the existing sewer main that crosses the rear of
the site. The easements shall generally be parallel to and centred over the sewer main and be
equivalent in width to twice the depth to invert level of the sewer at the deepest point within the
allotment (measured from the finished surface) and be no less than 3.0 metres wide.
In this regard, plans submitted for Operational Works approval shall accurately show the
location of the easement.
In addition to this the Applicant’s Solicitor shall give Council’s Solicitor an appropriate
undertaking in writing that the Title Deed and the easement documents will be lodged at the
Land Titles Office and any additional Titles Office forms or requisitions requiring the consent of
Council will be attended to promptly.
A duly executed copy of the easement shall be submitted to Council for perusal prior to the
use commencing.
Any changes required by Council’s Solicitor must be corrected immediately.
36. No building or other structure shall be constructed or encroach over an easement. Any
building or structure within proximity of an easement or any other public utility’s underground
must have its foundations designed so that no surcharge loads are imposed upon such
underground infrastructure. Foundations must be taken down a minimum of 1 metre below a
line of influence measured 1 metre in the direction of the foundation from the centreline of the
closest underground service and along the natural angle of repose of the foundation soil
type(s).
Plans, and supportive documents, detailing these proposed foundations shall be designed by
a registered practicing Geotechnical Engineer and submitted with the application for a
Development Permit for Operational Works.
Headworks
37. Contributions shall be paid to Council in accordance with Planning Scheme Policies PSP28
and PSP30 on Water Supply Headworks Contributions and Sewerage Headworks
Contributions respectively and at the rates applicable at the time of payment. An estimate
only of the contribution rates as of June 2004 under the current policies is as follows:
Water Supply $ 4,255
Sewerage $ 2,905
TOTAL $ 7,160
All headworks contributions must be paid prior to the issue of a Development Permit for
Operational Works.
Alternatively a trading bank guarantee shall be submitted to Council plus 20%. Should the
headworks contributions not be paid at the due time, Council shall call upon the trading bank
guarantee in full.
In the event that the Development Permit for Material Change of Use of Premises lapses or is
cancelled, the contribution or trading bank guarantee will be returned.
Page 5 of 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED Decision Notice - Change to an Existing Approval - 010.2003.00221172.002 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 69 KB (small file)
- File type
No other editions are linked here.