                                                                          VIRIDIAN III - Landscape Works

1.6       CONSTRUCTION PROGRAM

Three (3) construction programs are to be submitted to the Builder prior to commencement
of work for approval no less than seven (7) days following notification of being awarded the
contract. Advise if any of the documents are to be returned.

Construction program will clearly indicate the following information on a weekly basis:
   • Project Milestones
      •   Critical path of construction
      •   Tasks
      •   Progress

Contractor is to ensure the work is organised, sequenced, and implemented in a manner
which eliminates unreasonable disturbance to the site, property and disruption to continuing
property users, and access.

1.7       REFERENCED DOCUMENTS

Use latest editions of referenced documents and refer to any amendments. Other editions or
amendments required by statutory authorities will take precedence over referenced
documents.

Responsibilities and duties of the Principal, Contractor and Builder are not altered by
requirements in referenced documents.


1.8       CONNECTON TO SERVICES

The Contractor shall allow for the connection of all irrigation controllers to electrical mains
and shall be included as a rated fitting with the approval of Energex to avoid the installation
of a switchboard.

The Contractor shall similarly allow for the connection of the irrigation system to the mains
water supply including all costs associated and Noosa water charges.

1.9       SITE FACILITIES

The Contractor shall establish site sheds and storage facilities etc within the site area
provided to the head contractor. Water, electricity and toilet facilities will be provided for
connection at the nominated location.

1.10      PARKING & SITE YARD

The Contractor will arrange storage of materials on site in a nominated area within the head
contract site area. The Contractor shall remain fully responsible for the materials stored on
site.

1.11      MATERIALS & WORKMANSHIP

Where specified, materials which are not available or cannot reasonably be provided in time
to meet the program, the Builder will permit substitutions for such materials provided that
EDAW Aust                                 Page 5                       February 2008

Used in these records

About this file

File size
133 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Viridian III Technical Specification OPW1 [As Published].pdf · 133 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.