Viridian III Technical Specification OPW1 [As Published] · 142008.256
VIRIDIAN III - Landscape Works
1.6 CONSTRUCTION PROGRAM
Three (3) construction programs are to be submitted to the Builder prior to commencement
of work for approval no less than seven (7) days following notification of being awarded the
contract. Advise if any of the documents are to be returned.
Construction program will clearly indicate the following information on a weekly basis:
• Project Milestones
• Critical path of construction
• Tasks
• Progress
Contractor is to ensure the work is organised, sequenced, and implemented in a manner
which eliminates unreasonable disturbance to the site, property and disruption to continuing
property users, and access.
1.7 REFERENCED DOCUMENTS
Use latest editions of referenced documents and refer to any amendments. Other editions or
amendments required by statutory authorities will take precedence over referenced
documents.
Responsibilities and duties of the Principal, Contractor and Builder are not altered by
requirements in referenced documents.
1.8 CONNECTON TO SERVICES
The Contractor shall allow for the connection of all irrigation controllers to electrical mains
and shall be included as a rated fitting with the approval of Energex to avoid the installation
of a switchboard.
The Contractor shall similarly allow for the connection of the irrigation system to the mains
water supply including all costs associated and Noosa water charges.
1.9 SITE FACILITIES
The Contractor shall establish site sheds and storage facilities etc within the site area
provided to the head contractor. Water, electricity and toilet facilities will be provided for
connection at the nominated location.
1.10 PARKING & SITE YARD
The Contractor will arrange storage of materials on site in a nominated area within the head
contract site area. The Contractor shall remain fully responsible for the materials stored on
site.
1.11 MATERIALS & WORKMANSHIP
Where specified, materials which are not available or cannot reasonably be provided in time
to meet the program, the Builder will permit substitutions for such materials provided that
EDAW Aust Page 5 February 2008
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Viridian III Technical Specification OPW1 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 133 KB (small file)
- File type
No other editions are linked here.