3.5.2 RAINFALL DATA

As per the pre-development scenario and includes the 20% increase in rainfall intensities.


3.5.3 HYDROLOGICAL LOSSES & BX FACTOR

As per the pre-development scenario.


3.5.4 DETENTION TANK

Table 8 presents the detention tank parameters modelled. Refer to Appendix C for the stage vs area
relationship. Re-analysis will be required if the stage-area relationship is significantly altered.

                                         Table 8 – Detention Tank Details
                         Detention Parameter                                  Value
                     Surface Area (m²)                                         8.5
                     Volume (m³)                                              20.4
                     Depth (m)                                                 2.4
                     Tank IL (m AHD)                                          30.1
                     Orifice Outlet                            80mm dia at IL 30.1m AHD
                     Weir Outlet                            1500mm weir at RL 32.43m AHD



3.5.5 POST-DEVELOPMENT PEAK DISCHARGE

The XP-STORM was run for 63% AEP to 1% AEP storms with 15 to 180-minute standard durations. Table
9 and Table 10 present the peak flow results.

                           Table 9 – Pre & Post-Development Peak Flows (XP-STORM)
                                                         Peak Flow Results (m³/s)
                       63% AEP        39% AEP        20% AEP         10% AEP         5% AEP       2% AEP        1% AEP
     Post-Dev.
   (2100 rainfall        0.011         0.014          0.016           0.018           0.020        0.022         0.024
    intensities)
      Pre-Dev.
   (2100 rainfall        0.016         0.021          0.027           0.034           0.040        0.042         0.046
    intensities)
     Variance           -0.004        -0.008         -0.011          -0.015           -0.020       -0.020        -0.021




SITE BASED STORMWATER MANAGEMENT PLAN – Revision C                                      36 & 38 DUKE STREET, SUNSHINE BEACH
                                                      P a g e | 10

Used in these records

About this file

File size
8.5 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

JFP SBSMP Revision C.pdf · 8.5 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.