Prelim Construction Management Plan[1]
Plans and drawings
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn3. Construction Management
3.1 Approach
The major external constraints on the project are:
• Maintaining smooth traffic and pedestrians flow with minimal disruptions to Rene Street,
and
• Undertaking works with minimal impact on neighbours, in particular, adjoining commercial
and industrial properties.
Upon commencement, our project team’s immediate tasks will be to:
• Undertake a survey of the site and complete a dilapidation report of adjoining properties
and assets,
• Assess the existing structures on-site and prepare for removal,
• Confirm the locations of existing services and obtain all necessary permits and licences
and approvals, and
• Arrange for the installation of temporary services – power, water and sewer to service the
site works and the amenities.
3.2 Approvals
A Decision Notice for a Reconfiguring a Lot was issued by Noosa Council on 30/3/2022 (RAL21/0028).
This Preliminary Construction Management Plan has been prepared as part of the application
material for an Operational Works permit (to be assessed by Noosa Council).
Following the issuing of an Operational Works permit by Council, the below Certifications and
Approvals will be obtained:
• Certification from the service providers (Energex, NBN and Unitywater) which certifies that
the development has met the requirements of Council’s approval RAL21/0028 and all
applicable legislation at the time of construction.
• Confirmation of easement registration over the relevant service provider, public or third
party infrastructure located on the site.
3.3 Site Security
The site will be secured using appropriate fences with access gates manned with qualified security
guards/traffic control officers. The site will be secured out of hours and patrolled by qualified
security guards. All visitors to the site will be required to report to the site office, and will be
appropriately inducted and registered in a visitor’s log book.
RG Strategic Preliminary Construction Management Plan 5
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.