siren (on an annual basis) and will enter into a contract with a suitable service
contractor to maintain the flood height gauge and siren to BOM specifications. The
Body Corporate is responsible for ensuring such maintenance contract is in force at all
times.
19. The Body Corporate is responsible for advising all owners of the proposed lots of the
requirement for a service contract and of funding arrangements associated with the
ongoing operation, management and maintenance of the flood height gauge and siren
required by this approval. The Body Corporate is responsible for ensuring there are
adequate funds at all times to operate, manage and maintain the flood height gauge
and siren.
20. All dwellings must be constructed in accordance with the minimum habitable floor level
requirement of RL 3.5m AHD.
21. The Body Corporate is responsible for the overall communication, implementation, and
periodic update of the FEMP. A regular review of the FEMP shall be undertaken (at
least once every five years and immediately following a river flood event that floods
Lake Weyba Drive adjacent to the site).
22. The Body Corporate is responsible for ensuring that there is an active procedure for
notifying the owners and occupiers of the proposed lots of the potential for a flood and a
heavy rainfall event, and developing, maintaining and implementing emergency flood
procedures, in accordance with the FEMP.
23. The Body Corporate is responsible for advising the owners and occupiers of the
proposed lots that they are responsible for ensuring they have enough food, water, and
medical supplies to shelter in place for a minimum of three days.
External Road Works
24. Prior to the sealing of the plan of survey, the Applicant is to upgrade Lake Weyba Drive
for the full frontage of the subject site. The works are to include but not be limited to:
a. Kerb and channel on the same alignment as the existing section of kerb in Lake
Weyba Drive at the intersection of Furl Street;
b. Widening of the formation to extend to the new kerb line;
c. Suitable transitions / joints to the existing formation;
d. Suitable transitions to the north and south to smoothly join to the existing pavement
width;
e. Any associated drainage works required to drain the new road and the subject site.
Stormwater Drainage
25. The site must be provided with a stormwater drainage system connecting to a lawful
point of discharge. The works must be undertaken in accordance with an Operational
Works approval and in accordance with the Council’s standards.
Earthworks And Retaining Walls
26. All earthworks and associated retaining structures / batters, both above and below
ground, both temporary and permanent, must be undertaken in accordance with an
Operational Works approval, and contained entirely within the subject site unless
written permission from the respective landowner(s) is provided to Council.
4
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.