Water And Sewer Connections
27. An underground connection to reticulated water and sewerage must be provided to
each lot in accordance with the standards and requirements of Northern SEQ
Distributor – Retailer Authority (Unitywater).
28. A Certificate of Completion from the Northern SEQ Distributor – Retailer Authority
(Unitywater) must be submitted to Council that certifies an underground connection to
reticulated water and sewerage has been provided to each lot.
Services
29. Underground reticulated electricity and telecommunication services must be provided to
each lot in accordance with an approval for Operational Works and the standards and
requirements of the relevant service provider.
30. Unless otherwise stipulated by telecommunication legislation at the time of
construction, the development must be provided with all necessary conduits, pits and
pipes to accommodate the future connection of optic fibre technology
telecommunications.
31. Certification must be submitted to Council from all relevant service providers (Energex,
NBN) which certifies that the development has met the requirements of this Decision
Notice and all applicable legislation at the time of construction.
Easements
32. Easements for drainage purposes (overland flow of stormwater), as shown on Overall
development layout plan RL40 Revision A, must be registered in favour of Council.
The easements must be created as part of the sealing of the survey plan for the
development.
33. A public thoroughfare easement must be registered in favour of Council over the cul-de-
sac turnaround extension off Sail Street (private road). The easement must be created
as part of the sealing of the survey plan for the development.
34. A 4 metre wide easement for access purposes must be registered over the fire trail
shown on Overall development layout plan RL40 Revision A, in favour of Council and
Queensland Fire and Emergency Services. The easement must be created as part of
the sealing of the survey plan for the development.
35. Unless otherwise agreed in writing by the relevant service provider, any public or third
party infrastructure located on the subject site must be placed within an easement
registered against the title of the property.
36. All easements must be designed in accordance with the planning scheme and granted
at no cost to the Grantee. Where the Grantee is Council or a service authority, the
easement documentation must be in accordance with the Grantee’s standard easement
terms. Draft easement documentation must be submitted to Council for endorsement.
37. All works must be kept clear of any existing or proposed easements on the subject
land, unless agreed otherwise in writing by the Grantee.
Community Management Statement
38. A Body Corporate is to be constituted for the development.
39. A proposed Community Management Statement required for the development pursuant
to the Body Corporate and Community Management Act 1997 must be submitted to
Council for endorsement at the same time as submission of the subdivision plan.
5
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.