40. All clauses and by-laws of the proposed Community Management Statement must
accord with the requirements of this development approval and, in particular, must
include the requirements:
a. of the Flood Emergency Management Plan;
b. for the maintenance of the common property private cul de sac extension of Sail
Street, including access to the lot frontages of proposed lots 4-8;
c. of the Bushfire Management Plan;
d. of the Bushland & Wetland Rehabilitation Plan, for the ‘maintenance period’; and
e. of the vegetation preservation covenant required to be registered against the titles
of lots 3, 4, 7, and 8 in accordance with condition 50 of this Development Approval.
Damage To Services and Assets
41. Any damage caused to existing services and assets as a result of the development
works must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety,
immediately; or
b. where otherwise, upon completion of the works associated with the development.
42. Any repair work which proposes to alter the alignment or level of existing services and
assets must first be referred to the relevant service authority for approval.
Landscaping Works
43. The development site must be landscaped. The works must be undertaken in
accordance with an Operational Works approval and the Noosa Plan for that specific
area and must include in particular:
a. the works shown on the Approved Plans.
b. provision of 1 street tree within the road reserve for every 8 metres of road
frontage to Sail Street and Lake Weyba Drive.
c. removal of all weed species listed in the following standards and legislation:
i. declared plants under the Land Protection (Biodiversity Act 2016 and
subordinate Regulation 2016)
ii. Council’s Biosecurity Plan 2020 pest plant species listed in Schedule 1,
Part 3, Schedule 2 and Non-scheduled invasive species.
All entry statements, fences, batters, retaining walls and buffer-screen plantings must
be located entirely within private land and not within the public road reserve.
All landscape works must be maintained generally in accordance with the approved
design for the life of the development.
Estate Entrance Feature
44. Any proposed estate entrance feature must:
a. reflect a subdued local character, rather than an overbearing or contrived
statement.
6
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.