2020-08-31 SM - Item 2 - Attachment 2 - Infrastructure Agreement
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
17. Prior to the sealing of the survey plan, the private road within Lot 3 (Road C – adjacent
to lots 7-9) must be constructed with a centrally located 12m carriageway having 1.5m
on-road cycle lanes on each side. The works must be in accordance with an Operational
Works approval and be generally in accordance with drawings numbered 1856-R05
revision K and 1856-R07 revision J prepared by Barlow Shelley. The works must include
but not be limited to kerb and channel, 3m footpath on the western side, street lighting,
services, linemarking, stormwater drainage and landscaping. The road must be
designed to cater for on-street parking to be added when future development occurs on
lots 3 and 7.
18. Prior to the sealing of the survey plan, the entrance road between Lots 2 and 7 must be
constructed. The works must be in accordance with an Operational Works approval and
be generally in accordance with drawing number 1856-R17 revision J prepared by
Barlow Shelley. The works must include but not be limited to kerb and channel,
footpaths, street lighting, services, linemarking, stormwater drainage and landscaping.
Property Access and Driveways
19. Prior to the sealing of the survey plan access to the lots must be provided generally in
accordance with the access management plan shown on drawing numbered 1856-R03
revision J prepared by Barlow Shelley unless modified herein:
a. access to proposed for Lots 4, 8-10, 15, and 16 must 9.0m wide (minimum) and
be provided as part of subdivision operational works,
b. access to proposed Lots 3, 5, 6, 7 and 17-22 must be constructed as part of the
future development of the lots,
c. all movements access for lots 11-14 must be constructed as part of the future
development of the lots
Property notations will be added to Council’s rates records for Lots 3, 5, 6, 7, 11-14 and
17-22 advising owners, prospective purchasers and private certifiers of the access
requirements.
20. Vehicle access to Lots 4, 8-10, 15, and 16 is limited to the constructed driveway only. A
clause must be included in the contract of sale for Lots 4, 8-10, 15, and 16 which requires
vehicle access to be from the constructed driveway only, and which prohibits the
driveway from being relocated without Council agreement.
Emergency Access Route (Lots 11-15)
21. The 6m wide emergency access route through Lots 11-15 connecting Hofmann Drive
and Walter Hay Drive must be constructed. The works must be undertaken in
accordance with an Operational Works approval and be generally in accordance with
drawings numbered 1856-R04 revision K and 1856-R05 revision K prepared by Barlow
Shelley. The works must include but not be limited to:
a. locked gates controlling access at Hofmann Drive and Walter Hay Drive. The gates
are to be installed by the developer in land areas fully controlled by Council and
clear of any service allocations in the road reserve
b. the emergency access route, driveways and gates to Hofmann Drive and Walter
Hay Drive are to be designed to suitably accommodate all QFES vehicles that
could reasonably access the emergency access route.
22. In regard to the emergency access route, and adjacent parking along that route, at the
rear of lots 12-15:
Page 99
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.