Extension to Currency Period - Approved 132008.176.04 [AS PUBLISHED]
b. Planning Scheme Policy 13 – Contributions in Lieu of Off Street Parking;
c. Planning Scheme Policy 16 – Sewerage Headworks Contributions;
d. Planning Scheme Policy 17 – Water Supply Headworks Contributions;
e. Planning Scheme Policy 20 – Pathway Trunk Network Contributions;
f. Council Policy – Rural Roadworks Contributions; &
g. Council Policy – Master Drainage Contributions.
For material change of use of premises approvals the contributions must be paid prior to
the commencement of use, for reconfiguring a lot approval contributions must be paid
prior to Council approval of the plan of subdivision.
The actual amount of the contribution must be calculated and paid in accordance with
the Planning Scheme Policies and variations due to indexation current at the time of
payment.
General
89. Any Building Format Plans (or similar) submitted for Council approval must be
accompanied by the relevant Community Management Statement (or similar)
demonstrating compliance with the conditions of this approval.
90. A suitably qualified Registered Professional Engineer shall prepare engineering
drawings and specifications for all engineering works that will become Council
infrastructure, which shall be submitted in conjunction with an application for a
Development Permit for Operational Works. In this regard a DXF/DWG file on GDA94
zone 56 grid of the proposed cadastre layout is to be submitted in conjunction with any
application for Operational Works.
91. Digital detailed designs including drawings, calculations, specifications and a schedule
of works, shall be submitted with any application for a Development Permit for
Operational Works in respect of roadworks and stormwater drainage works. The design
shall be in accordance with Council’s Planning Scheme Policy PSP05 – Engineering
Design Standards – Roads, Drainage and Earthworks. To avoid conflict with
underground pipes or services, all existing and proposed services required by the
development shall be shown on the plans.
92. To facilitate production of As Constructed drawings it is suggested that all design
drawings are submitted in the Asset Design and As Constructed (ADAC) digital format.
(Guidelines on the use of ADAC are available at www.adac.com.au).
93. A construction management plan/strategy to ensure no damage occurs to Council
services shall be prepared by a suitably qualified Registered Professional Engineer and
submitted to Council in conjunction with any application for Operational Works.
94. Any damage caused to any public utility during the course of construction shall be
repaired to Council’s standards and at no cost to Council.
95. Any alteration of any public utility or other facilities necessitated by the development of
the land or associated construction works external to the site shall be at no cost to
Council.
96. The transportation of all materials to and from the site shall be undertaken in a manner
such that no particle matter escapes onto a public road. All vehicles carrying materials
either to or from the site shall be covered to prevent materials including dust being
windblown from the vehicle.
97. As Constructed drawings and data shall be certified by a qualified experienced Civil
Engineer for design intent, and a Licensed Surveyor shall certify the cadastre and the
Document Set ID: 23307313
Version: 3, Version Date: 24/10/2024 Page 12 of 20
See the original