BR190571 BP Noosaville - Preliminary Construction Management Plan

of 16

Page text shows just the words. Original shows the document exactly as it was published.

Original PDF page 6, section 1. The text section number identifies this passage in the reader.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
2         Project Overview
 2.1      Project Description
The BP project is located at 52-54 Mary Street, Noosaville QLD 4566 over lots described as Lot 21 on
RP72829 and Lot 1 on RP131598
The total area of the Development Area is approximately 0.249 hectares.
Refer to Appendix A for Site Survey.
Refer to Appendix B for Preliminary Site Plans.

 2.2      Site Context
The site is within proximity to;
    Retail
    Multi-unit dwelling developments
    Weyba Park West
    Neighbourhood streets
    Single-lot houses
As a result, all planning and co-ordination of the works will be undertaken with diligence and respect to
these groups. Notification will be provided (via letterbox drop and/or face-to-face meetings) to
neighbouring properties advising of the commencement of works, duration of the construction program,
and contact details of key personnel.

 2.3       Construction Staging
There will be five distinct stages of construction. These will have varied material handling and logistical
strategies in order to construct the building efficiently and minimise impact on the existing stores that
are to remain open during construction as well as surrounding streets and neighbours. The stages are:
    Stage 1 – Demolition of Existing Sheds and Building on Lot 21 RP72829
    Stage 2 – Trunk Sewer Diversion Works
    Stage 3 – Demolition & Removal of Existing Fuels Tanks
    Stage 4 – Building works for new BP store across the 2 lots.

 2.4      Construction/Works Program
Construction is programmed to commence in 2020 and be completed in 2021. Contractor to supply full
construction program once engaged.




 P:\BR19\BR190571 BP Noosaville\Reports\CMP\BR190571 BP Noosaville - CMP.docx                                 Page 6 of 13
Log in to download the original file

BR190571 BP Noosaville - Preliminary Construction Management Plan.pdf · 2.0 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.