Conditions 22 a and c are imposed pursuant to s128 of the Planning Act 2016 being
necessary trunk infrastructure identified by Council’s LGIP to service the
development.
23. Diamond Lane must be upgraded for the full length of the frontage to the subject site.
The works must be undertaken in accordance with an Operational Works approval
and must include in particular:
a. Road widening, refuse truck loading zone and kerb and channel;
b. removal of any redundant property accesses and reinstatement of the kerb and
verge area to match the upgraded frontage, including the provision of topsoil
and turf where required; and
Condition 23 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
24. The road verge along the frontage of the site to Opal Street must be upgraded in
accordance with an Operational Works approval and must include in particular:
a. a new 2.0m wide concrete pathway with adjusted alignment and construction
methods as necessary to protect the survival of existing street trees
b. construction of car and scooter parking in accordance with the Infrastructure
Agreement
c. Reinstatement and landscaping
Condition 24 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Pedestrian and Bicycle Facilities
25. Pedestrian and bicycle facilities must be provided for the development. The works
must be undertaken in accordance with an Operational Works approval and must
include in particular:
a. Internal pedestrian footpaths in accordance with the approved plans
b. a total of 8 bicycle parking spaces
c. end of trip facilities involving 4 lockers and 1 shower with ancillary change
rooms.
Public Safety
26. All ground floor shopfront glazing must be protected against vandalism by the use of
a form of safety glass such as toughened or laminated glass.
27. During operating hours, all parking areas, pedestrian areas and entrances/exits to all
stairwells, foyers and public toilets must be well lit with vandal resistant lighting and
with intensities to satisfy the requirements of Australian Standard AS1158 “Public
Lighting Code”. Lighting must be designed to reduce the contrast between shadows
and well lit areas. In particular, appropriate security lighting must be provided in the
location shown at the corridor servicing the toilets and change room.
Electricity and Telecommunication Services
28. Unless otherwise stipulated by telecommunications legislation at the time of
construction, the development must be provided with all necessary conduits, pits and
pipes to accommodate the future connection of optic fibre technology
telecommunications.
29. Certification must be submitted to Council from all relevant service providers which
certifies that the development has met the requirements of this Decision Notice and
all applicable legislation at the time of construction.
Page 39 of 133
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.