                      In this regard, specifications and plans detailing this work must be prepared in accordance
                      with Council’s Planning Scheme Policy 5 – Engineering Design Standards – Roads,
                      Drainage and Earthworks.
                      Site Access and Driveways
               20.    A sealed access driveway must be provided from Opal Street and Opal Lane to all parking
                      and manoeuvring areas of the development. The works must be undertaken in accordance
                      with an Operational Works approval and must include in particular driveway crossovers
                      generally in accordance with Council’s Standard Drawings RS-049 and RS-050.
                      Stormwater Drainage
               21.    The site must be provided with a stormwater drainage system connecting to a lawful point of
                      discharge.
               22.    All stormwater drainage (including roof water overflow from the rainwater storage system)
                      must be collected and discharged so there is no net increase in stormwater runoff from the
                      site. The works must be undertaken in accordance with an Operational Works approval and
                      be generally in accordance with the Proposed Duplex Integrated Water Management Plan –
                      Version 0 dated April 2019 prepared by Callaghan & Toth Civil, Environmental and Hydraulic
                      Engineers.
                      Electricity and Telecommunication Services
               23.    Reticulated electricity and telecommunication services must be provided to each lot in
                      accordance with the standards and requirements of the relevant service provider.
               24.    Unless otherwise stipulated by telecommunications legislation at the time of construction, the
                      development must be provided with all necessary conduits, pits and pipes to accommodate
                      the future connection of optic fibre technology telecommunications.
               25.    Certification must be submitted to Council from all relevant service providers which certifies
                      that the development has met the requirements of this Decision Notice and all applicable
                      legislation at the time of construction.
                      Easements
               26.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.
               27.    All easements must be designed in accordance with the planning scheme and granted at no
                      cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                      documentation must be in accordance with the Grantee’s standard easement terms. Draft
                      easement documentation must be submitted to Council for endorsement.
               28.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.
                      Earthworks and Retaining Walls
               29.    All earthworks and associated batters/walls must be contained entirely within the subject site
                      unless written permission from the respective landowner(s) is provided to Council.
                      Damage to Services and Assets
               30.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.



                                                                                                       Page 4 of 9
Document Set ID: 20860721
Version: 7, Version Date: 13/05/2019                                                                Print Date: 13 May 2019, 4:45 PM
Log in to download the original file

MCU.pdf · 4.2 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.