                                                         Reconfiguration of a Lot
                      When Conditions Must Be Complied With
               31.    Unless otherwise stated, all works required by the conditions of this Decision Notice must be
                      completed prior to submission of the subdivision plan to Council for compliance assessment.
                      Approved Plans
               32.    Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                           Plan No.              Rev.   Plan/Document Name                            Date

                           V.1 – 29.04           -      Site Cover Plan,         drawn    by   Toth 10/04/2019
                                                        Environmental

               33.    All lot numbering on the subdivision plan to be submitted to Council for compliance
                      assessment must remain as shown on the Approved Plans.
               34.    The development must be undertaken and operated in a manner that causes no detrimental
                      effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
                      lighting nuisance or other emissions.
               5.     REFERRAL AGENCIES

               Not applicable.
               6.     ADVISORY NOTES

                      Building and Construction Industry (Portable Long Service Leave) Levy
               1.     The QLeave levy must be paid prior to the issue of a development permit where it is required.
                      Council will not be able to issue a Decision Notice without receipt of details that the Levy has
                      been paid. QLeave contact: 1800 803 481 (free call) or (07) 3212 6855.
                      Co-ordination of Operational Works Assessment
               2.     Additional application fees apply to Operational Work applications where the different
                      aspects of the works are lodged separately. Significant savings in application fees will result
                      if all works are lodged in a single application.
                      Preparation of a Preliminary Construction Management Plan
               3.     A preliminary Construction Management Plan must be submitted with the Operational Works
                      application and must address the following:
                      a.      appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
                              Devices (MUTCD)
                      b.      provision for safe pedestrian access across the frontage of the site both during daily
                              construction and after daily construction has ceased.
                      c.      traffic management during all aspects of the construction phase including:
                              i.       a Traffic Management Control Plan in accordance with the Manual of Uniform
                                       Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
                                       control measures prior to construction.
                              ii.      maintenance of safe pedestrian access for the areas affected by the works during
                                       and after daily construction has ceased.
                              iii.     proposed fencing to the site during the construction phase of the development.
                              iv.      approval of the Traffic Management Control Plan by the Department of Transport
                                       and Main Roads (DTMR) for any works on State controlled roads.



                                                                                                          Page 5 of 9
Document Set ID: 20860721
Version: 7, Version Date: 13/05/2019                                                                   Print Date: 13 May 2019, 4:45 PM
Log in to download the original file

MCU.pdf · 4.2 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.