ORDINARY MEETING AGENDA                                                             29 MAY 2014


    22.23.     The fire-fighting demand on Unitywater’s water supply system from the
         development must not exceed 30 litres per second.
    23.24.      A single Unitywater installed primary water meter must be provided
         immediately inside the property boundary. Additional water meters must be installed
         for each title of a community title or sub-lease scheme. Meters must be Unitywater
         approved, installed in accordance with Unitywater requirements and remain
         accessible at all times for reading and maintenance purposes.
    24.25.       Water meters must be located on alternative boundaries to electrical pillars.
    25.26.     The existing Unitywater sewer infrastructure must be relocated clear of the
         proposed building works prior to commencement of excavation on site.
    26.27.     Written approval to enter and construct must be provided from property
         owners through which external sewers or relocated sewers traverse. This must be
         submitted with lodgment of the associated development application for Operational
         Works.
    27.28.      Easements of between 3 and 10 metres must be provided over all Unitywater
         sewers located within property boundaries in accordance with the SEQ standards.
         Easements shall be centred over the pipe. Easement terms shall be the most current
         registered dealing held by the Department of Natural Resources & Mines and shall
         not be altered or amended.
    28.29.      Buildings, basements and other structures must maintain a minimum
         clearance of 1.5 metres from Unitywater sewer mains, and 1.0 metre from a sewer
         manhole chamber or sewer inspection opening. Any proposed or existing retaining
         wall crossing Unitywater sewer mains must be self supporting for a minimum of 1.0
         metre each side of the sewer pipe and piered below the zone of influence of the
         sewer.
    29.30.       Storm water retention systems and gross pollutant traps must maintain a
         minimum clearance of 1.5 metres from Unitywater water supply and sewerage
         infrastructure.
    30.31.      Tree plantings must maintain a minimum horizontal clearance of 1.0 metre
         from Unitywater water mains and 1.5 metres from Unitywater sewerage mains.
         Landscaping plants within these clearances must be low growing when mature, and
         suitable approved varieties.
    31.32.      Construction works undertaken in the vicinity of Unitywater water supply or
         sewerage infrastructure must not adversely affect the integrity of the infrastructure. All
         costs associated with repair, replacement or alteration of infrastructure must be met
         by the applicant.
    Landscaping
    32.33.     The development site must be landscaped. The works must be undertaken in
         accordance with an Operational Works approval, Planning Scheme Policy 3
         Landscaping Plants and Guidelines and must include in particular:
          (a)   The works generally shown on the Approved Plans unless amended by these
                conditions
          (b)   A minimum 3.5m wide landscaped area on the David Low Way frontage within
                the site boundary, extending from the bus-stop to the intersection with the
                unnamed road, with at least 2.5m of the landscaped area at road level
          (c)   The transformer is not to be located within the landscape setback areas
          (d)   A minimum 2m wide landscaped area on the unnamed road frontage within the
                site boundary with at least 1.2m of the landscaped area at road level



                                                                                     Page 9 of 21
Log in to download the original file

2014-05-29 Ordinary Meeting Agenda(PDF, 488KB).pdf · 500 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.