GENERAL COMMITTEE MEETING AGENDA                                                                     29 JUNE 2015


5                        CONTRACT 1415T036 MUNNA POINT BRIDGE REHABILITATION (DESIGN AND
                         CONSTRUCTION)
DOCUMENT INFORM AT ION




Author                              Project Manager, Adam Britton
                                    Planning & Infrastructure Department

Index                               ECM/Projects (T1)/Noosa Parade Munna Point Bridge
                                    ECM/Subject/Contracting/Tenders

Attachments                         Nil


EXECUTIVE SUMMARY
Not Applicable.

RECOMMENDATION
That Council note the report by the Project Manager to the General Committee Meeting dated
29 June 2015 and
A.                       Award Contract 1415T036 Munna Point Bridge Rehabilitation (Design and Construction) to
                         Marine and Civil Maintenance Pty Ltd for the lump sum amount of $2,490,380 subject to
                         Marine and Civil Maintenance Pty Ltd satisfactorily responding to Council’s request for
                         information regarding their tender;
B.                       Allocate funding of $1,627,005 from the renewal infrastructure emergent works allocation in
                         the first quarter budget review of 2015/16; and
C.                       Delegate authority to the Chief Executive Officer to agree on any remaining items requiring
                         clarification.



REPORT
Following a report to the Infrastructure and Services Committee dated 31 March 2015, Council
staff prepared tender documentation for the Munna Point Bridge Rehabilitation (Design and
Construction).

The public tender was issued on 18 April 2015 through LG Tender Box as a design and
construction tender. The tender scope was based on a reference design prepared by local
consulting engineers Tod Consulting with specific performance outcomes including the
requirement for the rehabilitation to extend the bridge life by 50 years.

The tender documentation was downloaded over 100 times comprising a mixture of contractors,
consultants and individuals. As the works are highly specialised it was expected that the number
of submissions would be significantly lower.

Upon close of tenders on 12 June 2015, thirteen submissions were received including four firms
offering a submission based on the Principal supplied reference design and their own alternative
design.




                                                                                                     Page 25 of 28
Log in to download the original file

2015-06-29 General Committee Meeting Agenda(PDF, 602KB).pdf · 617 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.