Risk
Finance risks include;
Client request for scope changes. This is to be mitigated through project control group
management and limitation of client requested scope variations.
Latent conditions. Typically a geotechnical risk, previous investigations have mitigated much
of this risk.
Variation risks. This has been partly mitigated through the lump sum construction
procurement method utilised.
Time risks include;
Wet weather delays. Construction during the typically dry season aims to mitigate this.
Safety Risks;
Concrete Skateparks Pty Ltd would be appointed as the Principal Contractor and responsible
for Workplace Health and Safety of the site and the ultimate design and construction. Prior
to construction commencing, workplace health and safety and pedestrian and traffic
management plans will be required to be submitted to Council for approval. Regular audits
on contractor compliance with these approved plans will be undertaken by Council
throughout construction.
Scope & Quality Risk;
The risk of meeting project objectives is to be managed through Council staff reviews
supported by specialist consultants who developed the performance specifications.
Resource Risk;
Concrete Skateparks Pty Ltd have nominated a very capable team for this project limiting the
resourcing risks to the project. The addition of an engineering consultants, mitigates the
resourcing risk from Council.
External Consultation - Community & Stakeholder
Council officers have met and notified property and business owners in 2016 about the upcoming
works. The community were supportive of the skate park renewal.
Community consultation - skate day event, held at Sunshine Beach Skate Park - Saturday 23 April
2016.
Presentation of the draft concept design to community, users and stakeholders, held at the Noosa
Aquatic Centre - Friday 1 July 2016.
Internal Consultation
Finance, Procurement, Environment, Civil Operations and Asset Planning Teams.
Departments/Sections Consulted:
Community Services X Planning & Infrastructure
Disaster Management & Public Order Building & Plumbing Services
Waste & Environmental Health DA Planning
X Community Facilities Strategic Land Use Planning
Cultural Facilities X Asset Design & Investigations
X Asset Planning
X Civil Operations
Environment
Executive Office Corporate Services
X Community Engagement X Finance
Customer Service ICT
Executive Support X Procurement & Fleet
Governance Property & Facilities
Human Resources Revenue Services
Page 5 of 50
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.