2018-04-10 S&O Agenda - Attachment 1 to Item 6 - Sand Recycling System Asset Management Plan
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn11. ANNEX D: SRS Asset Maintenance Plan
Frequency
CH2M Duration
Asset Asset Asset Maintenance of task No. of
No. Id No. Description Asset Type Strategy Calendar Hours Discipline (hours) Staff Parts Consumables
Sea Water
10- 10- pump No.1 Predictive
WP1 WP1 Pump Pump Maintenance 1W Mechanical 0.5 1 $ - $ -
10- 10- Predictive
SP1 SP1 Slurry pump Pump Maintenance 1W Mechanical 0.25 1 $ - $ -
Preventive
Maintenance,
Slurry pump Routine
1047 1047 Motor Motor Maintenance 1W Mechanical 0.25 1 $ 10.00 $ 10.00
Preventive
Maintenance,
10- 10- High-pressure Routine
WP2 WP2 pump Pump Maintenance 1W Mechanical 0.25 1 $ - $ -
Preventive
Maintenance,
High-pressure Routine
1048 1048 pump Motor Motor Maintenance 1W Mechanical 0.25 1 $ 10.00 $ 10.00
10- 10- Low-pressure Predictive
WP3 WP3 pump Pump Maintenance 1W Mechanical 0.5 1 $ - $ -
Preventive
Maintenance,
Low-pressure Routine
1049 1049 pump Motor Motor Maintenance 1W Mechanical 0.25 1 $ 10.00 $ 10.00
Security
fencing and Predictive
1004 1004 access gates Fencing Maintenance 1M Mechanical 0.5 1 $ - $ -
Asset Management Plan: Noosa Main Beach Sand Recycling System Page 25