2018-04-10 S&O Agenda - Attachment 1 to Item 6 - Sand Recycling System Asset Management Plan
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn CH2M Duration
Asset Asset Asset Maintenance of task No. of
No. Id No. Description Asset Type Strategy Calendar Hours Discipline (hours) Staff Parts Consumables
Preventive
Sea Water Maintenance,
10- 10- pump No.2 Routine
WP4 WP4 Pump Pump Maintenance 1Y Mechanical 2 1 $ - $ 20.00
Preventive
10- Sea Water Maintenance,
WP4- pump No.2 Routine
01 Motor Motor Maintenance 1Y Electrical 1 1 $ - $ 10.00
Preventive
10- Maintenance,
SP2- Sand Clearing Routine
01 Pump Pump Maintenance 1Y Mechanical 3 2 $ 20.00 $ 20.00
Preventive
10- Maintenance,
SP2- Sand Clearing Routine
02 Pump Motor Motor Maintenance 1Y Electrical 1 1 $ - $ 10.00
Preventive
Sea Water Maintenance,
HV- HV- Intake Pump Routine
018 018 Check Valve Valve Maintenance 1Y Mechanical 0.5 1 $ - $ 10.00
Predictive
1050 1050 Switchboard Switchboard Maintenance 1Y Electrical 1 2 $ 25.00 $ 15.00
Preventive
10- Maintenance,
SP1- Routine
02 Slurry pump Pump Maintenance 1Y Mechanical 2 1 $ 50.00 $ 20.00
Preventive
Maintenance,
1047- Slurry pump Routine
01 Motor Motor Maintenance 1Y Electrical 1 1 $ - $ -
Asset Management Plan: Noosa Main Beach Sand Recycling System Page 29