Attachment 2 - Sealed Final Judgment
Attached to the e-mail Pre-Request Response Application - MCU14/0008.03.
The original of this document is very large (19.6 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
• 10pm to 7am: No audible noise.
Assessment and certification is required immediately after installation of the equipment
and prior to any occupation of the building. All equipment should be operating at the same
time to test the overall noise level created, with the measurement location at either the
residential boundary or outside the most exposed part of an affected building - whichever
is the closest to the plant/equipment.
30. The certification must be submitted to Council, which certifies that operational noise from
any fixed plant and equipment complies with the requirements of this Decision Notice.
UNITYWATER
31. Reticulated water supply and sewerage must be provided to the development.
32. Construction activities must not impede the access of Unitywater or Fire Brigade
personnel to vital infrastructure (eg. valves, fire hydrants and sewer access chambers).
33. The fire-fighting demand on Unitywater's water supply system from the development must
not exceed 15 litres per second.
34. The existing 150mm diameter asbestos concrete watermain in David Low Way must be
replaced for the full frontage of the development site with DICL pipes. The replacement
works must be completed prior to placing construction materials/site offices over or
adjacent to the water main alignment.
35. A single Unitywater installed primary water meter must be provided immediately inside the
property boundary. Additional water meters must be installed for each title of a community
title or sub-lease scheme. Meters must be Unitywater approved, installed in accordance
with Unitywater requirements and remain accessible at all times for reading and
maintenance purposes.
36. Water meters must be located on alternative boundaries to electrical pillars.
37. Buildings and other structures must maintain a minimum clearance of 1.5 meters from
Unitywater sewer mains, and 1.0 meter from a sewer manhole chamber or sewer
inspection opening.
38. The level of the existing sewer manholes must be adjusted to suit the proposed finished
surface levels. Work must be undertaken by Unitywater at the applicant's cost or by the
applicant's private contractors following submission to Council of an Operational Works
application and approval of the application.
39. Easements of between 3 and 10 metres must be provided over all Unitywater sewers
located within property boundaries in accordance with the SEQ standards. Easements
shall be centred over the pipe. Easement terms shall be the most current registered
dealing held by the Department of Natural Resources & Mines and shall not be altered or
amended.
40. Storm water retention systems and gross pollutant traps must maintain a minimum
clearance of 1.5 meters from Unitywater water supply and sewerage infrastructure.
41. Tree plantings must maintain a minimum horizontal clearance of 1.0 metre from
Unitywater water mains and 1.5 metres from Unitywater sewerage mains. Landscaping
plants within these clearances must be low growing when mature, and suitable approved
varieties.
Page 8 of 36
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.