Appendix D - Engineering Report
Table 5: Water Quality and Drainage Code – Criteria Assessment - Continued
Performance Outcome Project Outcome
Stormwater quality and protection of receiving waters
It is proposed to utilise the existing stormwater management
areas (vegetated buffers, vegetated swales, lake system)
constructed as part of the Noosa Springs Golf Resort. These
PO6 devices provide water quality treatment of stormwater flows
from the development site. Additional water quality treatment
will be provided using rainwater harvesting and reuse tanks with
total volume >100kL.
It is proposed to utilise existing stormwater management areas.
These devices use natural processes and are well integrated into
PO7 the landscape.
No proprietary treatment devices are proposed for use onsite.
PO8 Not Applicable.
PO9 Not Applicable.
Hydrology and waterway stability
The development proposal will utilise existing constructed
waterbodies which provide total capture of stormwater runoff
from the development site.
New carparking areas to the north will be constructed using
PO10 permeable materials (porous pavement, pavers interspersed
with turf etc.).
Proposed rainwater harvesting and reuse tank will reduce the
total volume of stormwater discharging to downstream
waterways.
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Appendix D - Engineering Report.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.