2018-07-06 SM - Attachment 1 to Item 5 - Level of Service Catalogue
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
Service Listing 1 of 1
Service Output STORMWATER DRAINAGE & FLOOD MITIGATION
Provision and maintenance of a stormwater drainage network and other
measures to minimise impacts to the road transport network, private
property and the environment.
Service Activity Maintenance
The activities include regular inspections and routine works to ensure
drainage lines are free flowing, that the impact of contaminants being
washed into the ocean/waterways is minimised, that flood mitigation
measures perform to design criteria and that accurate information is
available to respond to flooding events.
1
Responsible Area Department Branch
Infrastructure Services Civil Operations (Civil Works &
Maintenance)
Asset Management (Flood
alert/gauges)
Cost Centres Drainage 2005
Asset Management & Service 2105 (Flood Alert Stations / Height
Programming Gauges only)
Department Management – Director 1900
Infrastructure Services
Management Civil Operations 2000
Works Operations Coordination 2021
Works Operations 2704
2
Key Statistics # Stormwater Drainage assets 22,830 items
Length of stormwater drainage network 281 km
# Stormwater Quality Improvement 18 (major)
Devices’s (SQID’s - include gross 44 (minor installations)
pollutant traps, pit baskets, trash racks
etc.)
# Stormwater bio-retention basins 46
# Flood Alert Towers/structures 22
# Flood Alert Stations (tower in 23
Pomona has 2 stations on
structure)
Flood Alert - Repeater hardware - Mt 1
Wolvi
Food Alert - Telemetry receiver 1
hardware
Flood Maximum Height Gauges 46
Legislative responsibility to None.
provide this service
ACTIVITY SERVICE LEVEL TARGET
Stormwater system maintenance & operations
[Includes inspections and routine maintenance/repairs of culverts, pipes, inlet pits & outlets, subsoil drains, open
channels, retardation basins, retention basins and gross pollutant traps to ensure the stormwater drainage network is
operating effectively]
3
Cyclic Inspections Culvert/pipes inlets & outlets Six monthly
Major GPTs at Sunshine Beach, Noosa 4 times per year (quarterly)
Junction, Hastings St, Cooyar St.
Page 131
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.