5.10 MUSIC MODEL
The MUSIC model analysed for the proposed development site is shown in Figure 2.
Roof Area 1
Carpark 1 Carpark2
R ein a, 'e ns
Rainwater Tank Be-retention 1 Bio-retention
Outfall
Figure 2 -MUSIC Model Layout
5.11 MUSIC RESULTS
The MUSIC pollutant load reductions for the site are detailed in Table 17.
Table 17 - MUSIC results
MUSIC
Required Load Objective
Parameter Results
reduction Achieved
Achieved
Total Suspended Solids 80.0% 92.9% Yes
Total Phosphorus 60.0% 78.2% Yes
Total Nitrogen 45.0% 45.0% Yes
Gross Pollutants 90.0% 100.0% Yes
Table 17 demonstrates that the pollutant load reduction objectives for the site have been achieved. The water
quality devices proposed for the site are adequate in achieving satisfactory pollutant levels output from the site.
SITE BASED STORMWATER MANAGEMENT PLAN - Revision E % Gibson Road. Non 14
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.