4. Prior to Council endorsing the Plan of Survey, a certificate from a registered Professional Civil
Engineer shall be submitted to Council for each Development Permit for Operational Works
issued pursuant to this permit. The engineer shall certify those works and that they have been
completed in a workman like manner in accordance with good engineering practice and in
accordance with that permit.
Access (Road)
5. A new “Access” standard 5.5m wide sealed road as described in Council’s Planning Scheme
Policy PSP 5 Engineering Design Standards – Roads, Drainage and Earthworks shall be
constructed from Hollett Road extending approximately 25m past the end of the Lot 2 on
SP179590 access handle and terminating in a cul-de-sac, generally as shown on Drawing
Number M1775-12, prepared by Jones, Flint and Pike Pty Ltd and dated 19 May 2008. The
cul-de-sac for the new road shall have a minimum radius of 10 metres and all road verges
shall be topsoiled and grassed following completion of the roadworks in conjunction with the
Development Permit for Operational Works. A Development Permit for Operational Works
shall be obtained prior to the commencement of any works.
6. The road formation of Hollett Road frontage of the site shall be constructed to a “Collector”
standard 7m wide sealed road as described in Council’s Planning Scheme Policy PSP 5
Engineering Design Standards – Roads, Drainage and Earthworks. These works shall be
constructed to match smoothly with the existing road formation and include all necessary
tapers, drainage etc. A Development Permit for Operational Works shall be obtained prior to
the commencement of any works.
7. The intersection of the new road and Hollett Road shall be designed and constructed in
accordance with Council’s Planning Scheme Policy PSP 5 Engineering Design Standards –
Roads, Drainage and Earthworks and generally in accordance with the Department of Main
Roads Road Planning and Design Manual Chapter 13 Intersections at Grade part 13.7.10.1
“Basic Right Turn Treatment (BAR) on a two lane rural road. These works shall be constructed
to match smoothly with the existing road formation and include all necessary widening, tapers,
drainage etc. A Development Permit for Operational Works shall be obtained prior to the
commencement of any works.
8. The proposed names of new roads (public and private) and parks shall be lodged with the
application for a Development Permit for Operational Works.
Names are to be selected from any of the following categories:-
8.1. Easily pronounced words of Murri languages.
8.2. Names or words of local significance or historical interest.
8.3. Flora, fauna, industry, topographical, geological and similar features and terms relative
to the district.
8.4. Surnames of persons of merit or historical significance. (Personal names should be
avoided.)
Approval will not be given to a name that is the same or similar to the name of another road in
the Shire, or of a road in close proximity in a neighbouring Shire. Names that are not easily
pronounced, or may cause confusion to emergency services are to be avoided.
All street signs on new roads (public and private) and parks shall be erected prior to works
being accepted on maintenance.
Page 2 of 26
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2006.00002356.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 1.3 MB (small file)
- File type
No other editions are linked here.