Council archive · source document
Geotech Report · OPW26/0094
Project No. PG-10899 Page | 9 November 2023 Ref: PG-10899, 2023-10-16, GR VER 1 DD Sunnyside CD Sunnyside Pty Ltd – Geotechnical Investigation - Proposed Residence, 30 Mossman Court, Noosa Heads Foundation Design Parameters For footings founded 3m below the ground level, an allowable bearing capacity of 200kPa could be adopted, following confirmation that a minimum Density Index of 75% is present for a minimum depth of 750mm below the footings. If the exposed sands are disturbed or loosened during the excavation operation, they should be recompacted. Consideration should be given to placing a 50mm thick (minimum) concrete binding layer across the footings, immediately following excavation. Settlement Potential Settlements from underlying improved sands and natural soils beneath a pad footing of 2.5m width (i.e. maximum column load of 1500kN) at a nominal founding depth of 3.0m below existing ground level at a design bearing pressure of 200kPa have been calculated to be in the order of 15mm with anticipated differential settlements of between 25% and 50% of the calculated total settlement for pad footings founded at a similar depth. The settlement will occur as “immediate” settlement as the building loads are applied. Hydrostatic Uplift Forces For a fully tanked basement, hydrostatic uplift forces should be considered in the design. It is recommended hydrostatic uplift forces in groundwater levels to at least RL1.5 to 2.0m be taken into consideration on this site and checked for the Q100 flood condition. 12.0 DEWATERING CONSIDERATIONS Construction of the basement and foundation system will likely require dewatering. The groundwater will need to be lowered to a minimum of 0.9m below the final excavation depths, to allow the compaction of the founding soils to be achieved. Groundwater levels are expected to be similar to the tidal levels in the neighbouring canal. The HAT for Noosa Heads (Noosa River) is expected to be in the order of RL 1.07m and approximately 1.6m below ground level at the site. As the proposed excavation of up to 3m plus an additional 0.9m for ground improvements, where required, a drawdown of approximately 2 to 2.5m is therefore expected to be required. Dewatering is typically achieved through the use of perimeter spears and internal wells. Settlements inducted by 2m of drawdown (i.e. 20kPa effective stress increase) are estimated to result in settlements of less than 5mm. Therefore, it is considered that the effects of dewatering on the adjoining structures will be minimal.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Geotech Report.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.8 MB (small file)
- File type
No other editions are linked here.