GOOD SHEPHERD LUTHERAN COLLEGE ODYSSEY CONSULTING GROUP
Lot 30 on SP170751 Conceptual Stormwater Management Plan
115 Eumundi Noosa Road, Noosaville Project No: K4277
Post Development Modelling Results - Mitigated
The stormwater quality improvement device (SQID) will reduce the amount of sediments and
nutrients discharging from the proposed residential development. Table 18 illustrates the treatment
train effectiveness of the proposed SQID’s.
Table 18: Treatment Train Effectiveness of Proposed SQID
Parameter Post Post Mitigated Reduction (%) Water Quality Objectives
Flow (ML/yr) 6.66 6.57 1.5 -
TSS (kg/yr) 2590 461 82.2 80%
TP (kg/yr) 4.56 1.15 74.8 60%
TN (kg/yr) 21 10.5 49.9 45%
Gross Pollutants (kg/yr) 125 0 100 90%
The results demonstrate that the proposed SQID meet the intended water quality objectives for flow,
suspended solids, phosphorous and nitrogen levels.
6.0 OPERATIONAL PHASE MAINTENANCE REQUIREMENTS
The proposed stormwater management devices will require maintenance and monitoring to ensure
that they function as designed. The following section provides an outline of the necessary
maintenance tasks for the proposed devices.
6.1 Bio-retention Basin Maintenance
The most intensive period of maintenance is during the plant establishment period (first two years)
when weed removal and replanting may be required. It is also the time when large loads of
sediments could impact on plant growth particularly in developing catchments with poor building
controls.
Maintenance is primarily concerned with:
Maintenance of flow to and through the bio-retention basin;
Maintaining vegetation;
Preventing undesired overgrowth vegetation from taking over the bio-retention basin;
Removal of accumulated sediments; and
Litter and debris removal.
Vegetation maintenance will include:
Fertilising plants;
Removal of noxious plants or weeds; and
Re-establishment of plants that die.
Sediments accumulated at the inlets need to be monitored. Depending on the catchment activities
the deposition of sediment can tend to smother plants and reduce the ponding volume available.
Should excessive sediment build-up it will impact on the plant health and require removal before it
reduces the infiltration rate of the filter media. The proposed SQIDs will require regular maintenance
and monitoring to ensure that they function as designed.
K4277-0002-E 18 June 2019 Page 13 of 14
Document Set ID: 20894174
Version: 1, Version Date: 03/07/2019
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Approved Plans - MCU18-0097.pdfRelated documentApplication case desk ↗
About this file
- File size
- 3.7 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.