96.      All paths shall be designed and constructed to ensure pedestrian safety using non-slip materials and to
         produce an evenly graded surface finish.
Stormwater Drainage

97.      A stormwater management plan shall be prepared by a RPEQ, specialising in stormwater and water
         quality management incorporating the principles of the Environmental Management Plan for the Settlers
         Cove Development 23118 DA, that demonstrates water reuse strategies, infrastructure capacity and
         effective treatment methodology. The use of rainwater harvesting tanks for irrigation purposes shall be
         incorporated in the overall design plans. These plans shall be submitted to Council for approval prior to
         obtaining a Development Permit for Operational Works.

98.      All stormwater drainage shall be collected on site and discharged so there is no net increase in
         stormwater runoff from the site.

99.      On site swale drains will be required to capture and direct any overland stormwater runoff to the Infiltration
         Pits proposed on site. These swales shall be sized to carry a 3-month storm event and plans detailing
         their capacity, location, length, width and grades shall be submitted to Council for approval.

100.     To ensure polluted run-off does not enter any of the proposed Infiltration Pits, and ultimately the water
         table, stormwater run-off from the carparking areas and the driveways shall have the first flush (the first 12
         mm of rainfall or hose-down) collected in a grease/oil arrestor (or similar device) provided on site prior to
         discharging into the infiltration pits.
         To this end, a detailed maintenance plan shall be prepared for the proposed grease/oil arrestors, which
         shall be submitted to the Council for approval prior to obtaining a Development Permit for Operational
         Works.
         All other clean stormwater, such as roof water, can be collected on site and discharged directly into the
         infiltration pits, bypassing the grease/oil arrestor.
         A Development Permit for Building Works shall not be granted until a Development Permit for Operational
         Works has been issued in regard to the drainage scheme.

101.     All site stormwater drainage shall be by means of a gravity system.

102.     Plans of the entire on site drainage design shall be prepared by a Registered Professional Civil Engineer
         and submitted to Council prior to obtaining a Development Permit for Operational Works.
Sewer Mains

103.     The site shall be connected to Council’s existing sewerage reticulation systems and be constructed in
         accordance with Council’s standards and requirements at no cost to Council.
Town Water Supply

104.     The site shall be connected to Council’s existing town water supply and be constructed in accordance with
         Council’s standards and requirements at no cost to Council.

105.     Each water connection to the water reticulation system shall extend to the property boundary and be
         metered. Where multiple units are served by a single service, multiple water meters to each individual
         unit and for the body corporate shall be installed. All fees for the supply of water meters shall be paid to
         the Council.
Service Easements

106.     All existing and proposed easements within the site shall be shown on the plans submitted for Operational
         Works / Building Works approval.

107.     Registered easements shall be created over any Council service within the subject site in accordance with
         Council’s requirements (if not already created) and at no cost to Council.
         The Applicant’s Solicitor shall give Council’s Solicitor an appropriate undertaking in writing that the Title
         Deed and the easement documents will be lodged at the Land Titles Office and any additional Titles
         Office forms or requisitions requiring the consent of Council will be attended to promptly.
         A duly executed copy of the easement shall be submitted to Council for perusal prior to the use
         commencing.




SEP o:\database\onestop\decision.doc

Used in these records

About this file

File size
87 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

23117 DA COMPILED Decision Notice [As Published].pdf · 87 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.