25. The following must be complied with during the construction of the required
crossover/driveway:
a. The driveway surfacing must consist of either an approved hot mixed asphaltic
concrete or patterned/plain concrete.
b. The driveway must be constructed so as not to concentrate stormwater runoff onto
neighbouring properties
c. Where there is a pedestrian path, a matching crossfall must be provided for the
driveway on the alignment of the path, for the full width of the path
d. The property access must be located a minimum of 1m clear of existing power poles,
streetlights or other signage. The developer is responsible for any necessary relocation
of existing services to provide this clearance and must contact the relevant service
authorities and comply with their requirements in relation to these works.
Earthworks and Retaining Walls
26. All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines
on Earthworks for Commercial and Residential Development, with geotechnical testing
undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 1’ as
defined in Appendix B. Test results as required by AS 3798, and a certificate of quality and
uniformity of fill shall be provided by a RPEQ and submitted to Council prior to Council signing
the Plan of Survey.
27. Fall protection must be provided to retaining walls that are over 1m high
Stormwater Drainage
28. Appropriate scour protection must be provided at the outlet of all stormwater pipes including
temporary outlets.
29. Works associated with this permit must not adversely impact on the existing drainage
conditions on other properties (eg by blocking or interfering with natural overland flows).
30. Construction of all internal stormwater drainage works must comply with the relevant
section/s of Australian Standard AS/NZS 3500.3.
Environment
31. Prescribed Water Contaminants (as defined in the Environmental Protection Act 1994) must
not be released from the site or to waters within the site, or be likely to be released should
rainfall occur, unless all reasonable and practicable measures are taken to prevent or
minimise the release and concentration of contamination.
32. Erosion and sediment control measures must be installed and maintained to minimise
erosion on the site and to minimise the export of sediment and associated pollutants from
the site. The erosion and sediment control measures must be designed, installed and
maintained in accordance with current best practice standards (refer to advisory notes).
33. Prior to the completion of the development, all site surfaces must be effectively stabilised
using methods which have achieved effective short-term stabilisation and which will continue
to achieve effective stabilisation in the medium to long-term (refer to advisory notes). For the
purpose of this condition, an effectively stabilised surface is defined as one that does not, or
is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or
lead to sedimentation, or lead to water contamination.
Damage to Services and Assets
34. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Page 8 of 13
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.