Town Planning Report 18 Taylor Court Cooroy Rev A (1)
Attached to the e-mail Fw_ Email 3 of 3 - DA lodgement - 18 Taylor Ct Cooroy Lot 2SP197518 - Combined MCU_ OPW_ RAL under CTS (Pt 3).msg.
Code Assessment
Earthworks Code The bulk earthworks design and supporting information for 18 Taylor
(9.4.2) Court has been prepared to respond directly to the existing topography
of the site. Cut and fill extents are confined within the development
footprint with boundary retaining walls constructed wholly within the site.
Drainage is integrated into the earthworks design including graded
surfaces cut-off drains and collection to the on-site bio-retention and
detention basin ensuring no uncontrolled runoff or adverse impacts on
adjoining properties.
The staged layout enables progressive stabilisation of disturbed areas,
with erosion and sediment controls installed prior to upslope works to
achieve stability, containment, drainage and environmental protection.
Development complies with the purpose, overall and performance
outcomes or acceptable outcomes of the Earthworks Code.
Existing Services Development has been integrated with the existing services
Code (9.4.3) infrastructure including existing reticulated supply of water, stormwater,
sewer, electricity, telecommunications along the Taylor Court frontage
and within the service easements. The proposed crossover, internal
driveway layout and building design are coordinated around these
assets demonstrated in supporting information. Development responds
directly to the existing service network on and adjoining the site and can
achieve infrastructure provides requirements for protection, integration
and lawful connection.
Development complies or can be conditioned to comply with the
purpose, overall outcomes and performance outcomes or acceptable
outcomes of the Existing Services Code.
Fire Services for Development provides for suitable fire hydrant infrastructure which is
Common Private located to safely, efficiently and effectively access water supply and is
Title Code (9.4.4) integrated into the overall design of the development and reticulated
supply of water. Engineering design provides for unimpeded access for
QFES vehicles to fire hydrant infrastructure.
Development complies or can be conditioned to comply with the
purpose, overall outcomes and performance outcomes or acceptable
outcomes of the Fire Services for Common Private Title Code.
Landscaping Code Design provides for landscaping over 15.09% of the site (3,043m2) that
(9.4.5) enhance access points and allow passive surveillance which do not
impede on safety and security and provides partial landscape screening
of built form, elements, carparks, fences, utilities and storage areas at
maturity.
Development complies with the purpose, overall and performance
outcomes or acceptable outcomes of the Landscaping Code.
18
Town Planning Report - 18 Taylor Court Cooroy QLD 4563
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Town Planning Report 18 Taylor Court Cooroy Rev A (1).pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.