Town Planning Report 18 Taylor Court Cooroy Rev A (1)
Attached to the e-mail Fw_ Email 3 of 3 - DA lodgement - 18 Taylor Ct Cooroy Lot 2SP197518 - Combined MCU_ OPW_ RAL under CTS (Pt 3).msg.
Code Assessment
Reconfiguring a Lot The proposed Reconfiguring a Lot will create a Community Title
Code (9.5.1) Scheme for multiple tenancies / leases and the progressive creation of
each Staged Balance lot (standard format lot with common property)
requiring a community management scheme under the Body Corporate
and Community Management Act 1997.
An assessment against the relevant benchmarks of the code is included
in Appendix H.
Higher Order Approval
The development is subject to a higher order approval and MCU18/0120.01, OPW18/0197.01 &
RAL18/0013.01 - Development Permit for Material Change of Use - Industrial Type 2 Production,
Alteration, Repackaging & Repairing (39 Industrial Tenancies), a Development Permit for
Reconfiguration of a Lot (Access Easements), and a Development Permit for Operational Works
(Roadworks, Drainage Works, Landscaping, Stormwater, Earthworks, Car Parking & Access). The
proposal should ensure the development does not conflict with the higher order approval conditions.
Noosa Shire Council issued a Preliminary Approval in 2006 (Noosa Council Ref: 132005.2159) with
a Material Change of Use and Reconfiguration of a Lot (1 into 6 lots by Subdivision) at 34 Holts Rd
Cooroy (Lot 1444 CG3956). The higher order approval incorporated a Plan of Development (Figure
2) for the Nandroya Industrial Estate that includes the site with a schedule of provisions and planning
controls summarised in Table 8.
Table 8 – Higher Order (132005.2159) Plan of Development Provisions
Plan of Development Provisions Assessment
Setbacks Not Applicable
The existing Boral building is not affected by the provisions
relating to the development of the site.
Height Building or structure heights do not
The height of all buildings and structures are deemed to exceed 10m in and complies with the
comply if they do not exceed 10m planning control.
Water Quality Treatment Stormwater management plan is
Each allotment to treat stormwater runoff prior to exiting each included as supporting information to
allotment to the following standards: demonstrate development can comply
• Total Nitrogen of 0.3mg/L, with water quality objectives.
• Total Phosphorus of 0.03mg/L,
• pH - 6 - 8,
• Faecal Coliforms - 1000 organisms/100mL, and
• Suspended Solids - 15mg/L for combined wet and dry
periods: 90%ile < 100mg/L for wet weather periods.
Water Quality Treatment Stormwater management plan and
Each allotment shall submit a Stormwater and Water Quality engineering plans is included as
Management Plan that shall comply with and address inter supporting information to demonstrate
alia, the following issues in relation to the construction, development can comply with water
establishment and operation phases of the development: quality objectives and Erosion and
• All necessary erosion and sediment controls required. The sediment control best practices.
Erosion and Sediment Control Plans shall cover all
development on site (during the construction, establishment
and operational phases), ecological restoration and
remediation works.
• All necessary stormwater treatment and water quality
devices associated with the development shall be located
within the approved boundaries of the lots and each
development precinct.
20
Town Planning Report - 18 Taylor Court Cooroy QLD 4563
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Town Planning Report 18 Taylor Court Cooroy Rev A (1).pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.