24. All easements must be designed in accordance with the planning scheme and
granted at no cost to the Grantee. Where the Grantee is Council or a service
authority, the easement documentation must be in accordance with the Grantee’s
standard easement terms. Draft easement documentation must be submitted to
Council for endorsement.
25. All works must be kept clear of any existing or proposed easements on the
subject land, unless agreed otherwise in writing by the Grantee.
Earthworks and Retaining Walls
26. All fill and associated batters must be undertaken in accordance with an
Operational Works approval, and contained entirely within the subject site unless
written permission from the respective landowner(s) is provided to Council.
27. All retaining walls must be designed and constructed in accordance with the
planning scheme and must be certified by an RPEQ where exceeding 1.0m in
height. All retaining walls that are publicly accessible and exceed 1.0m in height
must be fitted with a commercial grade safety fence.
Damage to Services and Assets
28. Any damage caused to existing services and assets as a result of the
development works must be repaired at no cost to the asset owner at the
following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety,
immediately; or
b. where otherwise, upon completion of the works associated with the
development.
Any repair work which proposes to alter the alignment or level of existing services
and assets must first be referred to the relevant service authority for approval.
Landscaping Works
29. The development site must be landscaped prior to the commencement of use.
The works must be undertaken in accordance with an Operational Works
approval and the Noosa Plan for that specific area and must include in particular:
a. the landscape areas shown on the approved Site Plan/Floor Plan prepared
by Andrew McKellar Design dated 14.06.2017.
b. a minimum 2-metre-wide landscaping strip along the Ernest and Hilton road
frontage of the subject site, exclusive of the access driveway, generally
uncompromised by infrastructure items.
c. Any retaining walls must be setback from the front boundaries as shown
on the Approved Plans and screened with landscaping. Landscaping plans
must clearly show any retaining structure and adequately demonstrate how
these structures will be permanently screened with native vegetation.
d. all letterboxes located inside the development or in a position which does
not visually dominate the frontage.
e. details of the rendered wall finish on the Hilton terrace frontage, which can
include stone facing or other natural looking finishes and complement the
proposed landscaping.
Page 18 of 22
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.