Original source · versioned page text
2017-11-13 General Committee Meeting Notes
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING 13 NOVEMBER 2017
f. sub-terrain tree planting area demonstrating at least 4m³ area of structured
soils per tree is available for root growth and is not subject to compaction.
g. Provision of 100L Melaleuca quinquenervia along the frontage.
h. Details and depths of all landscaping soils, especially where subject to
compaction relating to filling of the site.
i. Plant selection generally as shown on the landscape documentation.
j. Bio-basin landscape plants must include a mixture of at least five of the
following species for planting in the bio-retention basin extended detention
surface at a minimum density of 8 plants/m²:
i. Carex appressa
ii. Carex fascicularis
iii. Ficinia nodosa
iv. Juncus usitatis
v. Lomandra longifolia
vi. Ghania sieberiana
30. All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures
healthy, sustained and vigorous plant growth. All plant material must be allowed
to grow to full form and be refurbished when its life expectancy is reached.
31. All landscape works must be maintained generally in accordance with the
approved design for the life of the development.
Stormwater Drainage
32. The site must be provided with a stormwater drainage system connecting to a
lawful point of discharge. The works must be undertaken in accordance with an
Operational Works approval and be generally in accordance with the submitted
Stormwater Management Plan - Revision A dated 19 April 2017, prepared by
Switchback 48 Consulting.
33. Stormwater runoff from the development must be disposed of on-site without
causing scour or damage to the subject site or any adjoining property. Plans
submitted for the Operational Works approval must include calculations in
accordance with Queensland Urban Drainage Manual for any overland flow
discharge areas to confirm that scour will not result from the development.
34. A stormwater quality treatment system must be provided for the development.
The works must be undertaken in accordance with an Operational Works
approval and the Bio-retention Technical Design Guidelines (Water by Design,
2012), and must include in particular:
a. stormwater quality treatment devices of a size and location of 30m2 plus
25m2 generally in accordance with those shown in section 2 of the of the
Stormwater Management Plan for 11-19 Hilton Terrace Tewantin by
Switchback Consulting, dated 19 April 2017.
b. Bio-retention devices which:
i. are designed generally in accordance with the Water by Design
Technical Design Guidelines for bio-retention basins
Page 19 of 22
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.