Construction Management Plan - Unit 15 The Hastings - 100217 · 51983.3225.06

Attached to the e-mail Construction Management Plan & Traffic Management Plan 51983.3225.06.

of 13

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
      3 Construction Methodology

      3.1 Demolition and Excavation

      The site is currently The Hastings unit complex. 16 separately titled and independently owned units make up the
      complex. Figure 2 presents and shows the layout and lot boundaries for unit.

      The existing building of Unit 15 will be progressively demolished until bulk earthworks can commence (Refer to
      Appendix – Demolition Plan DA.03).

       The Demolition Plan details the two trees which will be required to be removed for demolition and construction.

      Existing services within the site will be located and either capped if redundant or modified if they are to be used as
      temporary services for the works.



      3.2 Construction Sequence and Planning

      The locations and types of plant may vary depending on the results of more detailed planning as the design solidifies
      and the availability of plant is firmed up. There will be 3 distinct phases requiring different material handling logic to
      construct the building efficiently and minimise impact on surrounding streets and neighbours.

      The phases are:

              Phase 1 Site establishment; Demolition; Excavation and pile installation

              Phase 2. Structure Phase

              Phase 3. Finishes and external works

      Each Phase will not happen in isolation. Phase 2 and 3 will happen simultaneously once the structure is sufficiently
      complete to allow the finishes trades to commence on lower levels (Appendix - Gantt Chart).



      3.3 Rubbish Removal

      Rubbish will be removed from site by a licenced waste contractor ensuring that it is managed to comply with Noosa
      Council and their contractor’s requirements. It will be taken to the to a transfer facility.




CONSTRUCTION MANAGEMENT PLAN – FEB 2017                                                                RG STRATEGIC

Used in these records

About this file

File size
3.9 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Construction Management Plan - Unit 15 The Hastings - 100217.pdf · 3.9 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.