Council archive · source document
Referral Agency Response - Minor Change - RAP20 0003 01 [As Published] · RAP20/0003.01
11. Existing vegetation in the road reserve must be retained in accordance with the
conditions of this approval.
12. Trees to be retained must be protected from clearing or construction activities by:
a. clearly marking vegetation to be retained with flagging tape
b. installing protective fencing around the drip line of the vegetation
c. restricting stockpiling, storage and vehicle parking to those areas which are
already cleared
d. using low impact construction techniques around vegetation.
13. The two trees identified as Euca 0.71515 and Euca 0.51208 on the Noosa Cooloola
Land Surveys drawing 20316Det dated 13/03/2020 must be retained.
14. The alignment of the new sewer line and the decommissioning of the old sewer line must
be undertaken in a manner that avoids any works within the structural root zones (as
defined in AS 4970 -2009) of the two trees identified on the Noosa Cooloola Land
Surveys drawing 20316Det dated 13/03/2020 as, Euca 0.71515 and Euca 0.51208.
15. Any excavation or filling works within the Tree Protection Zone (as defined in AS 4970 -
2009) of the two trees on the Noosa Cooloola Land Surveys drawing 20316Det dated
13/03/2020 identified as Euca 0.71515 and Euca 0.51208 must be supervised by an
AQF Level 5 arborist, whose lawful directions must be adhered to.
16. Landscaping of the site must be in accordance with the Landscape Code, Planning
Scheme Policy 3 (PSP3) Landscaping Plants and Guidelines and must not use
undesirable species, as defined in PSP3.
Public Utilities and Services
17. Any conflict between the approved development works and an existing or proposed
service (eg sewer main) must be referred to the relevant service authority for
determination prior to commencement of works.
18. Any works in proximity to an existing or proposed service (eg sewer main) must be
carried out in consultation and compliance with the requirements and/or approval of the
relevant service authority.
Driveway and Pavement
19. A sealed access driveway and crossover must be provided from the street to carparking
on the site generally in accordance with the approved plans. The works must be
undertaken in accordance with an engineering design and Operational Works approval
and must include/address in particular:
a. A driveway crossover generally in compliance with IPWEA standard drawings RS-
049 and RS-050 with grades in accordance with the relevant requirements of
AS2890.1 and must have profile that ensure that standard vehicles entering or
exiting the site will not bottom down or scrape (the driveway surface or/and the
road pavement).
b. The driveway shall be generally 3.0m wide and must not exceed 4.0m width at the
kerb line.
c. The driveway within the road reserve must be constructed of an approved
pavement type.
d. The works must not adversely impact on existing natural vegetation and trees.
e. The works must include any necessary reinstatement of disturbed vegetation
along the shoulders of the driveway.
Page 4 of 8
Document Set ID: 22383616
Version: 3, Version Date: 27/04/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Referral Agency Response - Minor Change - RAP20 0003 01 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 148 KB (small file)
- File type
No other editions are linked here.