Original source · versioned page text
Meeting papers
SERVICES & ORGANISATION COMMITTEE MEETING 11 JULY 2023
Item Cost (ex GST)
Current spend to date $9,295
Construction Contract - Civil $409,904
Staff Time $15,301
Contingency (5%) $20,500
TOTAL BUDGET: $ 455,000
Risk & Opportunities
Finance Risks Mitigation
Changes to scope This is to be mitigated through the Capital Works Project Control
Group and Capital Works Executive meetings, and limitation
requested scope variations.
Geotechnical conditions A detailed Geotechnical investigation report has been completed
give rise for contractor and the report provided as part of the tender documentation.
claiming variation costs.
Clashes with public The contractor is aware of potential UnityWater clashes with the
utility provider Unity scope of works and will investigate the full relocation
Water give rise for requirements immediately after contract award. An allowance for
contractor claiming lowering of services has been made in the schedule of rates.
variation costs.
Contingency amount This risk is mitigated through Council's highly experienced project
being insufficient. team and the appointment of an experienced contractor and
contract supervision by an experienced Superintendent. If the
contingency amount is insufficient to cover the cost, this is to be
mitigated through the budget approval process.
Program Risks Mitigation
There is the potential Contractor has submitted a time-generous program which will
that the project is allow for wet days to be absorbed within the program. The works
delayed due to wet are also scheduled in the dry season.
weather.
Resource risk. The contractor has nominated a capable and experienced project
team to undertake the required construction works.
Construction takes The contractor is well-resourced and has the available resources
longer than allowed for to deliver this project successfully in conjunction with current
works on hand.
Lead time of materials Many associated risks are mitigated by ordering the materials as
pushing the program soon as possible after the tender award.
out.
Page 6 of 8
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original