SERVICES & ORGANISATION COMMITTEE MEETING 11 JULY 2023
Safety Risks Mitigation
Site safety. The contractor has submitted extensive safety documentation as
part of their submission and will be appointed as the Principal
Contractor, being responsible for all Workplace Health and Safety
of the site.
Prior to construction commencing, workplace health and safety
and construction management plans will be required to be
submitted to Council for review.
Regular audits on contractor compliance with these approved
plans will be undertaken by Council and WH&S teams throughout
the construction.
Environmental Harm Mitigation
Risks
Works impact on the The contractor is responsible for the development and
environment. implementation of strategies to minimise impacts such as noise,
dust, vibration, sediment, and erosion. The contractor is required
to submit a detailed Environmental Management Plan as well as
a CPESC approved Erosion and Sediment Control Plan prior to
construction.
Scope and Quality Mitigation
Risks
Risk of not meeting To be managed through reviews performed by an experienced
project objectives. Project Manager, Superintendent, and other project team
members.
Public Disruption Mitigation
Risks
Traffic disruption. Arkana Drive will remain open during the works with minor delays
to be expected. Resident access will be available at all times.
Communication issues. Council’s internal Infrastructure communications and consultation
Officer is appointed to the project and will help coordinate the
communications and consultation to community members.
Noise from plant and This will be minimised by working during normal working hours
equipment may be a where possible.
cause of disruption to
residents.
Consultation
External Consultation - Community & Stakeholder
Nil
Internal Consultation
Departments/Sections Consulted: