-6-
effective measures to mitigate potential increases in flow levels from the
development.

Refer Drawing DE07731/02 included in Appendix A for further details.

1.6 Flooding

With reference to Noosa Council Natural Hazard: Landslide and Flooding
Overlay Map (OM4.3), the subject site is not within the Q100 Flood Prone Area.

Refer Appendix A for extract from overlay map.

2.0 RAINWATER REUSE

With reference to Noosa Council Designated Rainwater Tank Area Map, the subject site
is within an area that requires rainwater tanks. Schedule 8 of the Noosa Planning
Scheme requires a minimum storage capacity of 3000 litres per dwelling unit. In addition,
water from the rainwater tanks is to be used for.

a) Flushing of toilets internal to the building;

b) Extemal irrigation, topping up of swimming pools or water features and outside
cleaning.

All rainwater tanks are to be designed and installed as per the Queensland Development
Code (QDC), Part 25 — Rainwater Tanks.

Refer Duke Environmental Drawing DE07731/02 in Appendix A for proposed location of
rainwater tanks.

3.0 HYDROLOGY
3.1 Methodology

It is proposed to mitigate the effects of the proposed development on stormwater
discharge rate by way of incorporating a Detention Basin.

This system is proposed to capture runoff from the site to maintain design
discharges up to, and including, the 100 year ARI event, from pre to post
development scenarios (non-worsening). Refer to Drawing DEO7731/02 included
in Appendix A for details.

Three different hydrological cases were investigated for the purpose of this study:

Case 1: Pre-Development site (existing)
Case 2: Post-Development of site (without mitigation)
Case 3: Post Development with mitigation strategies implemented

(Detention Basin)

The XP-RAFTS Run-off Routing Software was used for hydrological analysis of
the pre and post development catchments. Table 4.1 summarises adopted
discharge rates for the design critical storm duration, and the corresponding
rational method discharge. Refer Appendix B for internal site hydrologic
calculations and variables.

 

4A07731SMP
January 2008
ATijs

oe ge ieee

Used in these records

About this file

File size
20.7 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

09_1382 - Operational Works - Landscaping & Civil Works [As Published].pdf · 20.7 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.