Transport, Roads and Drainage Code
Specific Outcomes Acceptable Solutions/Probable Solutions Compliance
No solution provided Refer to Civil Engineering Report.
O11 Roads and stormwater drainage infrastructure is proven
to be suitable for its use prior to Council accepting the
dedicated asset.
S12.1 The location, design and construction of stormwater drainage Refer to Civil Engineering Report.
O12 Alignment of stormwater drainage infrastructure is to structures is in accordance with Sections 4 and 5 of PSP5, Engineering
allow for easy access for the ongoing maintenance by Design Standards - Roads, Drainage and Earthworks;
Council. AND
S12.2 Where infrastructure is located on private land an easement is Refer to Civil Engineering Report.
dedicated over the infrastructure in accordance with Section 4 of PSP 5,
Engineering Design Standards – Roads, Drainage and Earthworks.
14.148 Frontage works
S13.1 The following infrastructure components already exist at the Refer to Civil Engineering Report.
O13 Development is provided with external roadworks along frontage of the site or are provided at the developer’s expense—
the full extent of the frontage of the site to an appropriate a) full width sealed road;
standard having regard to the specified function of the road. b) concrete kerb and channel where appropriate;
c) forming and grading to footpaths;
d) vehicular kerb and footpath crossings;
e) a constructed bikeway;
f) a constructed footpath;
g) a constructed carriageway;
h) required alterations to public utility mains, services or installations;
i) construction of any required alterations to public utility mains,
services or installations;
j) stormwater drainage works; and
k) installation of electrical conduits;
AND
S13.2 Road and drainage design and construction is in accordance with
page 9
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.