Frontage Reinstatement Works
25. All redundant driveways and existing kerb laybacks along the frontage of the
site must be removed and the kerb, footpath and verge area reinstated to
match the balance of the site frontage, including the provision of topsoil and turf
where the existing verge is grassed. The works must be undertaken in
accordance with an Operational Works approval and must include in particular:
a. The existing driveway layback be removed and the kerb reinstated to
match the type and alignment of the adjoining existing sections of kerb
line. The driveway layback must be saw-cut and removed to allow for a
smooth and neat join finish between the new and the existing kerb.
b. Reinstatement of concrete footpath to provide even and consistent
gradients in longitudinal and across profiles generally in compliance with
IPWEAQ standard drawing SEQ R-065 Concrete Pathway Construction
Details, this may necessitate replacement of sections of the existing
footpaths beyond the edges of the redundant driveways and the frontage
of the site.
c. Any affected trees within the grassed verge must be replaced with similar
species in accordance with the landscaping conditions of this permit.
Car Parking
26. A minimum of 54 car parking spaces must be provided and marked on the site
generally in accordance with the approved plans. The works must be
undertaken in accordance with an Operational Works approval and must
include in particular:
a. 3 disabled parking spaces within the total.
b. 3 visitor parking spaces within the total, which are clearly marked for that
purpose and accessible at all times for visitor use.
c. 18 bicycle parking spaces.
d. Dimensions, crossfalls, gradients and vehicle headroom in accordance
with Australian Standard AS2890: Parking Facilities.
27. All car parking areas and access driveways must be maintained exclusively for
vehicle parking and maneuvering and kept in a tidy and safe condition at all
times.
28. All car and bicycle parking areas must be line marked in accordance with
approved plans, no dividing walls be constructed unless a further application for
amendment is approved by Council.
Stormwater Drainage
29. The site must be provided with a stormwater drainage system connecting to a
lawful point of discharge. The works must be undertaken in accordance with an
Operational Works approval, and must include in particular:
a. Stormwater system that caters for all storms up and including 1 in 100
years storm event.
b. No adverse impact on other properties and the road’s footpath and
grassed verge (eg by diverting flows and/or blocking flows and causing
additional ponding).
c. Where applicable, extension of the site stormwater system to
accommodate stormwater from external site, including registration of
drainage easements.
Page 24 of 89
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.