Attachment D Construction Manangement Plan · 132003.221152.5

Attached to the e-mail 132003.221152.5 - Response to further information - Part 2.

of 6

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
1.3 CLEARING

  The proposed development retains all the significant trees on the property. A
  number of smaller trees previously planted by the owner of No. 12 Park Road
  will be removed to allow access and for construction of footings. (Refer to
  Survey/Engineering Plans). On completion a similar tree will be replanted in
  each original location on site and in the road reserve.

  Prior to construction all trees will be clearly tagged and recorded on a survey
  plan. On completion the trees will be resurveyed to ensure full compliance
  with the conditions of the Development Approval.

  The regrading of the slopes (to improve overall long term stability) beneath
  the terrace will disturb the existing vegetation. On completion it is proposed
  to replant beneath the terrace with shade tolerant native species.


1.4 ACCESS AND PARKING

  The access for construction materials and equipment will be from Park Road
  via the existing driveway to No. 10 Park Road. The Builder is to submit
  written consent for the use of this access driveway and garage from the
  owner of No. 10 Park Road. Access for personnel will be via Allambi Rise
  and Park Road. Off site parking will be required for most construction
  personnel.

  Most workers vehicles shall be parked in Allambi Rise or in the existing
  driveway and carport of 12 Park Road which is accessed by the 9A driveway
  Allambie Rise.



1.5 MATERIALS HANDLING

  As previously described all building materials will be delivered to site via Park
  Road.      Manual material handling will be employed throughout the
  construction to minimise construction activities and impact on the site,
  especially existing vegetation. In addition a temporary builder’s hoist may be
  installed to deliver smaller building materials and to facilitate the easy
  removal of waste.

  Building waste will be collected and removed daily in a garbage trailer or light
  truck located adjacent to the garage of No.10 Park Road. In order to
  minimise waste and hence its removal, most building materials will be pre-
  engineered and delivered to site pre-cut to the appropriate size.

Used in these records

About this file

File size
871 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment D Construction Manangement Plan.pdf · 871 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.