Deliveries will be by light truck (6T) in small loads which will be manhandled
to site
At this stage it is envisaged that the following elements will be pre-
engineered prior to delivery:
Screw piles
Reinforcing steel
Timber framing for formwork
Scaffolding and formwork support
1.6 CONSTRUCTION PROGRAMME
The proposed Construction Programme is summarised below:
Operation Month 1 Month 2 Month 3 Month 4 Month 5 Month 6
Site Establishment
#
New Access Path
#
Construct Working Platform
#
Install Screw Piles
#
Construct Pipe Caps
#
Erect Formwork
#
Construct Concrete Structure
(Columns and Slab) #
Install Stormwater Reticulation
#
Install Landscaping
#
1.7 ENVIRONMENT MANAGEMENT PLAN
The method of construction does not require the use of a crane. This offers
significant environmental advantages as summarised below:
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment D Construction Manangement Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 871 KB (small file)
- File type
No other editions are linked here.